2425 N AVENUE 33 90065
Certificate Information: 2425 N AVENUE 33 90065
- Application / Permit
- 22016-20000-05494
- Plan Check / Job No.
- B22VN02895
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) 20'x46 ATT. 4-CAR GARAGE AND PORTION OF LAUNDRY ROOM TO NEW ATT. ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 1/25/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2022 | SEAN SHAHMIRI |
| Corrections Issued | 4/7/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 4/14/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| Applicant returned to address corrections | 10/17/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 10/17/2022 | SEAN SHAHMIRI |
| Issued | 1/25/2023 | APPLICANT |
| CofO in Progress | 1/29/2024 | RONALD JIMENEZ |
| Permit Finaled | 1/31/2024 | ERNESTO CORRAL |
| CofO Issued | 1/31/2024 | ERNESTO CORRAL |
| Permit Finaled | 1/31/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/2/2022 | JEANIE LAM |
| Address approval | Cleared | 5/3/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | JEANIE LAM |
| Specific Plan | Cleared | 7/7/2022 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 8/22/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Diversified Build; Lic. No.: 1033675-B | 4871 W WASHINGTON BLVD LOS ANGELES, CA 90019 |
| Engineer | Mehdizadehnasrabadi,, Mohammad; Lic. No.: C85373 | 705 W 9TH STREET UNIT 2306 LOS ANGELES, CA 90015 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/22/2023 | Approved | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 3/31/2023 | Corrections Issued | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/7/2023 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Concrete | 4/10/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 4/18/2023 | Partial Approval | RAMAZANALI ALMASI |
| Green Building Rough | 5/18/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 5/18/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 5/31/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 5/31/2023 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 7/7/2023 | Partial Approval | RAFAEL CORTES |
| Insulation | 7/18/2023 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 7/27/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 7/27/2023 | Approved | RAFAEL CORTES |
| Drywall Nailing | 8/3/2023 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 8/4/2023 | Approved | RAFAEL CORTES |
| Final | 1/12/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 1/12/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 1/12/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 1/12/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 1/12/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 1/22/2024 | Conditional Approval | RONALD JIMENEZ |
| Green Building Final | 1/22/2024 | Approved | RONALD JIMENEZ |
| Green Building Rough | 1/22/2024 | Approved | RONALD JIMENEZ |
| Smoke Detectors | 1/22/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 1/22/2024 | Approved | RONALD JIMENEZ |
| Final | 1/29/2024 | OK to Issue CofO | RONALD JIMENEZ |