8556 W VENICE BLVD 90034
Certificate Information: 8556 W VENICE BLVD 90034
- Application / Permit
- 22016-20000-05485
- Plan Check / Job No.
- X22VN01084
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Window (5 ) and door (3 ) change-out (same size & type) for residential buildings. Replace drywall (no new walls added) for single family dwellings and duplexes only. Replacement of damaged framing members (less than 10% of replacement cost of building) for houses and duplexes (not including decks). Replace drywall (no new walls added) for single family dwellings and duplexes only.
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/4/2024
Permit Application Status History
| Issued | 3/1/2022 | APPLICANT |
| Permit Finaled | 1/4/2024 | FARHAD DADBIN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2022 | Partial Inspection | NICK LAROCCA |
| Special/Order Compliance | 7/7/2022 | Partial Inspection | NICK LAROCCA |
| Special/Order Compliance | 8/2/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 8/2/2022 | Partial Inspection | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 1/4/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 1/4/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 5/2/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 5/4/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 5/10/2023 | Approved | FARHAD DADBIN |
| Drywall Nailing | 5/15/2023 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 5/26/2023 | Approved | FARHAD DADBIN |
| Final | 9/12/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Smoke Detectors | 9/12/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 12/7/2023 | No Access for Inspection | FARHAD DADBIN |
| Smoke Detectors | 12/7/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 12/11/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Smoke Detectors | 12/11/2023 | Approved | FARHAD DADBIN |
| Final | 1/4/2024 | Permit Finaled | FARHAD DADBIN |