1805-1807 E IMPERIAL HWY 90059
Certificate Information: 1805-1807 E IMPERIAL HWY 90059
- Application / Permit
- 22016-20000-05416
- Plan Check / Job No.
- B22VN02864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT EX. MEDICAL OFFICE INTO DUPLEX. INTERIOR REMODEL THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2022 | ROSENDO MEDINA |
| Corrections Issued | 3/5/2022 | ROSENDO MEDINA |
| Applicant returned to address corrections | 5/17/2022 | YAQUB MIRZA |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Applicant returned to address corrections | 7/23/2022 | ROSENDO MEDINA |
| Plan Check Approved | 8/11/2022 | ROSENDO MEDINA |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 6/21/2025 | DAVID FEILER |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
| CofO Issued | 6/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 3/16/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | JEANETTE VONG |
| Miscellaneous | Cleared | 7/13/2022 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/22/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/26/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 9/26/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/26/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/11/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/20/2022 | Corrections Issued | JOHN KLARIN |
| Shower Pan | 10/20/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/26/2022 | Approved | JOHN KLARIN |
| Wood Frame | 10/26/2022 | Approved | JOHN KLARIN |
| Final | 12/12/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 12/12/2022 | Approved | JOHN KLARIN |
| Special/Order Compliance | 3/13/2025 | Partial Inspection | ANTHONY EGSON |
| Final | 6/21/2025 | OK to Issue CofO | DAVID FEILER |