16647 W RUNNYMEDE ST 91406

Certificate Information: 16647 W RUNNYMEDE ST 91406

Application / Permit
22016-20000-05405
Plan Check / Job No.
B22VN02857
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 18' X 20' GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/1/2022
Issuing Office
Current Status
CofO Issued on 9/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 PINANK PATEL
Corrections Issued 2/25/2022 PINANK PATEL
Plan Check Approved 5/1/2022 PINANK PATEL
Issued 5/1/2022 APPLICANT
Building Plans Picked Up 5/2/2022 APPLICANT
CofO in Progress 9/1/2023 RAUL OLAGI
CofO Issued 9/26/2023 RUBEN SALAS
Permit Finaled 9/26/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/28/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/28/2022 CARLOS AGUILERA
Sewer availability Cleared 2/28/2022 CARLOS AGUILERA
Construction near power lines Cleared 4/11/2022 RIDWAN HARDY
Construction within easement Cleared 4/11/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/26/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/26/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 6/6/2022 Approved ALAN MORELOS
Underground Mechanical 6/6/2022 No Access for Inspection ALAN MORELOS
Wood Frame 7/6/2022 Corrections Issued CALEB MEISTER
ELECTRICAL-Rough 7/11/2022 Approved JOHN KIDWELL
PLUMBING-Rough 7/11/2022 Approved JOHN KIDWELL
Wood Frame 7/11/2022 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/15/2022 Approved RAUL OLAGI
Green Building Rough 8/15/2022 Approved RAUL OLAGI
HVAC-Rough 8/15/2022 Approved RAUL OLAGI
Insulation 8/15/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 8/15/2022 Partial Approval RAUL OLAGI
Shower Pan 8/15/2022 Not Ready for Inspection RAUL OLAGI
Drywall Nailing 9/14/2022 Approved RAUL OLAGI
Shower Pan 9/14/2022 Approved RAUL OLAGI
Final 6/20/2023 No Access for Inspection RAUL OLAGI
Green Building Final 6/20/2023 No Access for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/20/2023 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 6/20/2023 No Access for Inspection RAUL OLAGI
ELECTRICAL-Final 7/17/2023 Corrections Issued RAUL OLAGI
Final 7/17/2023 Corrections Issued RAUL OLAGI
HVAC-Final 7/17/2023 Approved RAUL OLAGI
PLUMBING-Final 7/17/2023 Corrections Issued RAUL OLAGI
Smoke Detectors 7/17/2023 Approved RAUL OLAGI
Final 8/8/2023 Corrections Issued RAUL OLAGI
Green Building Final 8/8/2023 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Not Ready RAUL OLAGI
Final 9/1/2023 OK to Issue CofO RAUL OLAGI
Green Building Final 9/1/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved RAUL OLAGI