7854-7856 W APPERSON ST 91040

Certificate Information: 7854-7856 W APPERSON ST 91040

Application / Permit
22016-20000-05394
Plan Check / Job No.
B22VN02846
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: CONVERT (E) ATTACHED GARAGE IN SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 5/11/2022
Issuing Office
Current Status
CofO Issued on 4/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 DANIEL YIP
Corrections Issued 3/11/2022 DANIEL YIP
Applicant returned to address corrections 4/7/2022 DANIEL YIP
Applicant returned to address corrections 4/18/2022 DANIEL YIP
Plan Check Approved 5/5/2022 DANIEL YIP
Issued 5/11/2022 APPLICANT
CofO in Progress 3/24/2023 DAVID ANDERSON
Permit Finaled 4/5/2023 DANIEL ORRANTE
CofO Issued 4/5/2023 DANIEL ORRANTE
Permit Finaled 4/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/30/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/30/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/14/2022 DAGOVERTO GUERRERO
Work Adjacent to Public Way Cleared 4/14/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/29/2022 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 9/7/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 9/7/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/8/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/8/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval DAVID ANDERSON
Green Building Rough 11/8/2022 Approved DAVID ANDERSON
HVAC-Rough 11/8/2022 Approved DAVID ANDERSON
PLUMBING-Rough 11/8/2022 Approved DAVID ANDERSON
Insulation 11/17/2022 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 11/17/2022 Approved DAVID ANDERSON
Drywall Nailing 12/29/2022 Approved DAVID ANDERSON
Final 3/14/2023 No Access for Inspection DAVID ANDERSON
Green Building Final 3/14/2023 No Access for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 3/14/2023 No Access for Inspection DAVID ANDERSON
Final 3/22/2023 Corrections Issued DAVID ANDERSON
Green Building Final 3/22/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 3/22/2023 Not Ready for Inspection DAVID ANDERSON
Final 3/24/2023 OK to Issue CofO DAVID ANDERSON
Smoke Detectors 3/24/2023 Approved DAVID ANDERSON
Service/Power Release 3/28/2023 Approved DAVID ANDERSON