13930-13932 N BERMAX AVE 91342

Certificate Information: 13930-13932 N BERMAX AVE 91342

Application / Permit
22016-20000-05300
Plan Check / Job No.
B22VN02776
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATT GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22. ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 1/31/22. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE."
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 1/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 HAYATO TSUCHIYA
Corrections Issued 3/3/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 4/11/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 5/6/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 6/1/2022 HAYATO TSUCHIYA
Plan Check Approved 7/8/2022 HAYATO TSUCHIYA
Building Plans Picked Up 7/11/2022 APPLICANT
Issued 7/13/2022 APPLICANT
Permit Expired-Status Void 1/10/2023 JOHN COLEMAN
Re-Activate Permit 1/30/2023 JOHN COLEMAN
CofO in Progress 1/4/2024 KEVIN BERBERYAN
No Progress 1/4/2024 ROBERT GOLD
CofO in Progress 1/5/2024 ROBERT GOLD
CofO Issued 1/22/2024 RUBEN SALAS
Permit Finaled 1/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/7/2022 JOSE DUARTE-DIAZ
Permit Cleared 3/7/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/7/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/16/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 4/11/2022 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2022 Corrections Issued ARAM AVEDISIAN
Deputy Drilled-In Anchors 7/28/2022 Partial Approval ROBERT GOLD
Footing/Foundation/Slab 7/28/2022 Approved DAVID ANDERSON
PLUMBING-Rough 7/28/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 8/8/2022 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Rough 8/8/2022 Not Ready for Inspection DEANDRE HOFFMAN
BUILDING-Rough-Frame 9/28/2022 No Access for Inspection ARAM AVEDISIAN
Insulation 9/29/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 10/13/2022 Corrections Issued DEANDRE HOFFMAN
Rough-Elec/Plmb/HVAC 10/13/2022 Corrections Issued DEANDRE HOFFMAN
ELECTRICAL-Rough 1/4/2023 Corrections Issued ARAM AVEDISIAN
Green Building Rough 1/4/2023 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 1/4/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 1/4/2023 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/6/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 1/6/2023 Approved ARAM AVEDISIAN
Green Building Rough 1/6/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/6/2023 Partial Approval ARAM AVEDISIAN
Insulation 1/9/2023 Permit Expired-Status Void JOHN COLEMAN
Drywall Nailing 2/1/2023 Corrections Issued WILLIAM WREN
Drywall Nailing 2/8/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 2/13/2023 Corrections Issued MATTHEW NELSON
Drywall Nailing 2/15/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/28/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 2/28/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 3/6/2023 Approved MATTHEW NELSON
Final 7/13/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 7/13/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/13/2023 Approved MICHEL ABAJAN
Service/Power Release 9/18/2023 Corrections Issued KEVIN BERBERYAN
Final 10/23/2023 Conditional Approval KEVIN BERBERYAN
Final 1/4/2024 OK to Issue CofO KEVIN BERBERYAN