817 W WEST 34TH ST 90089

Certificate Information: 817 W WEST 34TH ST 90089

Application / Permit
22016-20000-05251
Plan Check / Job No.
B22VN02744
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
eplan: Shoring for 1) Seismic retrofit to meet the requirements of the NDC of an existing church building. 2) addition (on 3-levels including basement) on the northwest side of the existing building. 3) Change of use from (E) church building to a performing arts venue and classrooms for USC associated with plan check 21014-10000-02290 Attn: Larry Lee
Permit Issued
Issued on 6/7/2022
Issuing Office
Current Status
Permit Finaled on 2/6/2024

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 LARRY LEE
Corrections Issued 3/22/2022 LARRY LEE
Quality Review Completed 3/23/2022 CHARLES CHANG
Plan Check Approved 6/2/2022 LARRY LEE
Issued 6/7/2022 APPLICANT
Permit Finaled 1/17/2024 LUIS CCAMACHO

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 8/18/2022 Conditional Approval ERNESTO CORRAL
Deputy Grading 8/19/2022 Conditional Approval ERNESTO CORRAL
Piling/Pier/Caisson 8/24/2022 Approved RUSSELL BONVOULOIR
Deputy Grading 8/25/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/26/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/29/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/30/2022 Conditional Approval WINSTON DUNNING
Deputy Grading 8/31/2022 Conditional Approval WINSTON DUNNING
Final 5/18/2023 Not Ready for Inspection ALAN MORELOS
Final 1/17/2024 Permit Finaled LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Not Required LUIS CCAMACHO
Smoke Detectors 1/17/2024 Approved LUIS CCAMACHO