21625 W DEVONSHIRE ST 91311

Certificate Information: 21625 W DEVONSHIRE ST 91311

Application / Permit
22016-20000-05227
Plan Check / Job No.
B22VN02734
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CHANGE OF USE AND MERGE 4 TENANT SPACE INTO ONE RETAIL STORE.
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/23/2022 JOE VO
Corrections Issued 3/14/2022 JOE VO
Applicant returned to address corrections 4/25/2022 JOE VO
Applicant returned to address corrections 4/27/2022 JOE VO
Plan Check Approved 6/15/2022 JOE VO
Issued 7/1/2022 APPLICANT
CofO in Progress 7/2/2024 DEANDRE HOFFMAN
Permit Finaled 7/16/2024 JEFFREY DURAN
CofO Issued 7/16/2024 JEFFREY DURAN
Permit Finaled 7/16/2024 JEFFREY DURAN

Permit Application Clearance Information

ZA Case Cleared 4/11/2022 STEVEN WECHSLER
"D" conditions Cleared 4/12/2022 STEVEN WECHSLER
"Q" conditions Cleared 4/12/2022 STEVEN WECHSLER
Sewer availability Cleared 4/19/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/20/2022 JOSE DUARTE-DIAZ
DAS Clearance Cleared 5/16/2022 JOE VO
Green Code Cleared 5/17/2022 AARON COSTA
Specific Plan Cleared 6/13/2022 SARAH HOUNSELL

Contact Information

Contractor West American Design And Development Inc; Lic. No.: 641213-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Partial Approval DANIEL VARNUM
Deputy Drilled-In Anchors 12/5/2022 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 1/26/2023 Partial Approval DEANDRE HOFFMAN
Special/Order Compliance 6/14/2023 No Access for Inspection DEANDRE HOFFMAN
Green Building Rough 6/26/2023 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 6/26/2023 Corrections Issued DEANDRE HOFFMAN
Green Building Rough 7/6/2023 Partial Inspection DEANDRE HOFFMAN
Wood Frame 7/6/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 7/18/2023 Approved DEANDRE HOFFMAN
Insulation 7/18/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 7/24/2023 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 3/29/2024 Partial Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Partial Inspection DEANDRE HOFFMAN
Wood Frame 5/8/2024 Approved DEANDRE HOFFMAN
Final 6/20/2024 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Final 6/20/2024 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Not Ready DEANDRE HOFFMAN
Smoke Detectors 6/20/2024 Approved DEANDRE HOFFMAN
Final 7/2/2024 OK to Issue CofO DEANDRE HOFFMAN
Green Building Final 7/2/2024 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Approved DEANDRE HOFFMAN