230 1/2 E 56TH ST 90011

Certificate Information: 230 1/2 E 56TH ST 90011

Application / Permit
22016-20000-05059
Plan Check / Job No.
B22VN02654
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/11/2022
Issuing Office
Current Status
CofO Issued on 6/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 DANIEL YIP
Corrections Issued 2/25/2022 DANIEL YIP
Plan Check Approved 3/11/2022 DANIEL YIP
Issued 3/11/2022 APPLICANT
CofO in Progress 6/13/2023 BRENDAN MORELLI
Permit Finaled 6/17/2023 DEROLD HAUFF
CofO Issued 6/17/2023 DEROLD HAUFF
Permit Finaled 6/17/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/1/2022 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 3/1/2022 ABEL CASILLAS
Sewer availability Cleared 3/1/2022 ABEL CASILLAS
Community Plan Implem. Overlay Cleared 3/8/2022 HELEN JADALI

Contact Information

Contractor Paars Inc; Lic. No.: 998847-B       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/1/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/3/2022 Partial Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 6/27/2022 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 6/27/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Sewer 7/1/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 7/1/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/7/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 7/7/2022 Approved JOAQUIN GREENOUGH
Sewer 7/7/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 7/7/2022 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/15/2022 Approved JOAQUIN GREENOUGH
Insulation 7/15/2022 Approved JOAQUIN GREENOUGH
Wood Frame 7/15/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 7/29/2022 Approved JOAQUIN GREENOUGH
Green Building Rough 7/29/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 7/29/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 7/29/2022 Approved JOAQUIN GREENOUGH
Shower Pan 7/29/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 10/21/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/21/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 10/21/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 10/21/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 10/21/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Final 10/21/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/21/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 10/21/2022 Approved ALIZAH MAYAGOITIA
Final 1/20/2023 OK to Issue CofO BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved BRENDAN MORELLI