9742-9744 N BEACHY AVE 91331

Certificate Information: 9742-9744 N BEACHY AVE 91331

Application / Permit
22016-20000-05056
Plan Check / Job No.
B22VN02653
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
ePlan Existing 20' x 20' two-car attached garage will be converted to Junior ADU
Permit Issued
Issued on 7/7/2022
Issuing Office
Current Status
CofO Issued on 12/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2022 APPLICANT
Assigned to Plan Check Engineer 3/4/2022 ARSALAN SHABESTARI
Corrections Issued 3/4/2022 ARSALAN SHABESTARI
Assigned to Plan Check Engineer 3/5/2022 ARSALAN SHABESTARI
Corrections Issued 3/14/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 3/14/2022 ARSALAN SHABESTARI
Applicant returned to address corrections 6/2/2022 ARSALAN SHABESTARI
Plan Check Approved 6/24/2022 ARSALAN SHABESTARI
Issued 7/7/2022 APPLICANT
CofO in Progress 10/27/2023 MICHEL ABAJAN
Permit Finaled 12/29/2023 RUBEN SALAS
CofO Issued 12/29/2023 RUBEN SALAS
Permit Finaled 12/29/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/8/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CARLOS AGUILERA
Sewer availability Cleared 3/8/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2022 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 8/3/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 8/3/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 8/3/2022 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 8/8/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 8/10/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 8/15/2022 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 8/15/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/22/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 9/22/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 9/22/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/5/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/5/2022 Approved MICHEL ABAJAN
Gas Test 10/5/2022 Approved MICHEL ABAJAN
Insulation 10/17/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/17/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved MICHEL ABAJAN
Drywall Nailing 1/24/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 5/31/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 6/6/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 6/13/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/28/2023 Approved MICHEL ABAJAN
Final 7/28/2023 Corrections Issued MICHEL ABAJAN
HVAC-Final 7/28/2023 Approved MICHEL ABAJAN
PLUMBING-Final 7/28/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 7/28/2023 Approved MICHEL ABAJAN
Final 10/27/2023 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Approved MICHEL ABAJAN