5225 N STROHM AVE 91601

Certificate Information: 5225 N STROHM AVE 91601

Application / Permit
22016-20000-05048
Plan Check / Job No.
B22VN02651
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) RECROOM (373 SF) INTO ADU, ATTACHED ADU PER ORDINANCE
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
CofO Issued on 10/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2022 APPLICANT
Assigned to Plan Check Engineer 3/9/2022 CARLOS MONTES
Corrections Issued 3/9/2022 CARLOS MONTES
Plan Check Approved 3/29/2022 CARLOS MONTES
Issued 5/3/2022 APPLICANT
CofO in Progress 10/26/2022 CALEB MEISTER
Permit Finaled 10/26/2022 MICHAEL SMITH
CofO Issued 10/26/2022 MICHAEL SMITH
Permit Finaled 10/26/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/19/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/21/2022 JOSE DUARTE-DIAZ
Tenant Habitability Plan Cleared 3/22/2022 MICHAEL SOTO
Sewer availability Cleared 3/24/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/6/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 6/6/2022 Corrections Issued MATT KELLERMAN
HVAC-Rough 6/6/2022 Corrections Issued MATT KELLERMAN
PLUMBING-Rough 6/6/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 8/5/2022 Approved ALAN MORELOS
HVAC-Rough 8/5/2022 Approved ALAN MORELOS
Insulation 8/5/2022 Partial Approval ALAN MORELOS
PLUMBING-Rough 8/5/2022 Approved ALAN MORELOS
Rough-Elec/Plmb/HVAC 8/5/2022 Approved ALAN MORELOS
Wood Frame 8/5/2022 Approved ALAN MORELOS
Insulation 8/15/2022 Approved JOHN HAYES
Interior/Exterior Lathing 8/15/2022 Partial Approval JOHN HAYES
Drywall Nailing 8/22/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 9/30/2022 Not Ready for Inspection JOHN HAYES
Final 9/30/2022 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/30/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/11/2022 Not Ready for Inspection JOHN HAYES
Final 10/11/2022 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 10/11/2022 Not Ready for Inspection JOHN HAYES
Verify Rec and Parks Fee Memo 10/18/2022 Approved CALEB MEISTER
BUILDING-Rough-Frame 10/26/2022 Approved CALEB MEISTER
Final 10/26/2022 OK to Issue CofO CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved CALEB MEISTER
Smoke Detectors 10/26/2022 Approved CALEB MEISTER