201-201 1/2 W 62ND ST 90003

Certificate Information: 201-201 1/2 W 62ND ST 90003

Application / Permit
22016-20000-04844
Plan Check / Job No.
B22VN02592
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT SFD TO DUPLEX, UNIT 1 (707 SF) AND UNIT 2 (746 SF).
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
CofO Issued on 6/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 CARLOS MONTES
Corrections Issued 2/25/2022 CARLOS MONTES
Plan Check Approved 4/20/2022 CARLOS MONTES
Issued 4/21/2022 APPLICANT
CofO in Progress 6/8/2023 BRENDAN MORELLI
Permit Finaled 6/15/2023 DEROLD HAUFF
Permit Finaled 6/15/2023 DEROLD HAUFF
CofO Issued 6/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/14/2022 TREVOR QUAN
Sewer availability Cleared 3/14/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/21/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/6/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 5/6/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 5/6/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 6/6/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/11/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 8/2/2022 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 8/2/2022 Partial Approval JOAQUIN GREENOUGH
Gas Test 8/26/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/26/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 9/1/2022 Approved ENRIQUE MIRELES
Insulation 9/12/2022 Partial Inspection MICHAEL LEWIS
PLUMBING-Rough 9/12/2022 Approved MICHAEL LEWIS
Pre-Inspection 10/5/2022 Approved HORACE FULTZ
Drywall Nailing 10/18/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/18/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 10/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 11/8/2022 Approved LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 11/16/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 11/16/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 12/21/2022 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 3/14/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 3/14/2023 Corrections Issued BRENDAN MORELLI
Final 3/14/2023 Corrections Issued BRENDAN MORELLI
HVAC-Final 3/14/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 3/14/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 3/14/2023 Corrections Issued BRENDAN MORELLI
Smoke Detectors 3/14/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 4/5/2023 Approved BRENDAN MORELLI
Final 4/5/2023 Not Ready for Inspection BRENDAN MORELLI
Gas Test 4/5/2023 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 4/5/2023 Approved BRENDAN MORELLI
PLUMBING-Final 4/5/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved BRENDAN MORELLI
Service/Power Release 4/5/2023 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 4/5/2023 Approved BRENDAN MORELLI
Final 4/24/2023 Corrections Issued BRENDAN MORELLI
Gas Test 4/24/2023 Corrections Issued BRENDAN MORELLI
Service/Power Release 4/24/2023 Approved BRENDAN MORELLI
Gas Test 5/1/2023 Approved BRENDAN MORELLI
Service/Power Release 5/19/2023 Approved BRENDAN MORELLI
ELECTRICAL-Final 6/7/2023 Approved BRENDAN MORELLI
Final 6/7/2023 OK to Issue CofO BRENDAN MORELLI