13358 N JAMIE AVE 91342

Certificate Information: 13358 N JAMIE AVE 91342

Application / Permit
22016-20000-04819
Plan Check / Job No.
B22VN02574
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE THE EXISTING 23'-4" X 9'-4" FRONT PATIO AND REMODEL SINGLE FAMILY DWELLING ALL WORK PER ENGINEER
Permit Issued
Issued on 3/21/2022
Issuing Office
Current Status
Permit Finaled on 5/15/2023

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/22/2022 DANIEL ABRAMYAN
Corrections Issued 2/22/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 3/10/2022 DANIEL ABRAMYAN
Issued 3/21/2022 APPLICANT
Building Plans Picked Up 3/22/2022 APPLICANT
Permit Finaled 5/15/2023 ARAM AVEDISIAN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/2/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/1/2022 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/1/2022 Approved JOHN HAYES
Footing/Foundation/Slab 4/1/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 4/15/2022 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 4/15/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 4/19/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved JOHN HAYES
PLUMBING-Rough 4/19/2022 Approved JOHN HAYES
Pre-Inspection 4/19/2022 Approved JOHN HAYES
Insulation 4/22/2022 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 4/22/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/26/2022 Not Ready for Inspection JOHN HAYES
Insulation 4/29/2022 Approved JOHN HAYES
Drywall Nailing 5/4/2022 Approved JOHN HAYES
Final 2/6/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 2/6/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 2/6/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 5/15/2023 Permit Finaled ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 5/15/2023 Approved ARAM AVEDISIAN