7746-7748 N IRVINE AVE 91605
Certificate Information: 7746-7748 N IRVINE AVE 91605
- Application / Permit
- 22016-20000-04810
- Plan Check / Job No.
- B22VN02572
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT, AND ENCLOSE THE (E) PATIO AND CONVERT TO A (N) REC. ROOM TO THE (E) SFD.
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2022 | PINANK PATEL |
| Corrections Issued | 4/5/2022 | PINANK PATEL |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 11/21/2022 | PINANK PATEL |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 10/8/2024 | MATTHEW NELSON |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
| CofO Issued | 1/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 5/3/2022 | STEVEN WECHSLER |
| ZI | Cleared | 5/3/2022 | STEVEN WECHSLER |
| Address approval | Cleared | 5/5/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 5/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/5/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/18/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/18/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/13/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/18/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 4/28/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 5/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 5/22/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 5/26/2023 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 5/26/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/1/2023 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 6/1/2023 | Partial Approval | MATTHEW NELSON |
| Pre-Inspection | 6/1/2023 | Corrections Issued | MATTHEW NELSON |
| Insulation | 6/6/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/6/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | MATTHEW NELSON |
| Insulation | 6/13/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/11/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 7/14/2023 | Corrections Issued | DAVID MATSON |
| Interior/Exterior Lathing | 7/26/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 7/26/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | MATTHEW NELSON |
| Final | 2/21/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/21/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 2/21/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 2/21/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/14/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/21/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 3/21/2024 | Partial Approval | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Final | 4/8/2024 | Partial Approval | MATTHEW NELSON |
| Green Building Final | 4/8/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/8/2024 | SGSOV Approved | MATTHEW NELSON |
| Final | 4/17/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 4/17/2024 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 4/23/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 4/23/2024 | Approved | MATTHEW NELSON |
| Insulation | 5/3/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 5/3/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 5/7/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Gas Test | 5/7/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Drywall Nailing | 5/10/2024 | Approved | MATTHEW NELSON |
| Gas Test | 5/10/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 6/25/2024 | Approved | MATTHEW NELSON |
| Final | 9/6/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 10/7/2024 | OK to Issue CofO | MATTHEW NELSON |