1937 S CAMDEN AVE 90025
Certificate Information: 1937 S CAMDEN AVE 90025
- Application / Permit
- 22016-20000-04754
- Plan Check / Job No.
- B22VN02526
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- DEMOLISH PORTION OF (E) DETACHED GARAGE EXCEPT 4' OF FOUNDATION AND REBUILD 16'-0" x 18'-0" (SAME SIZE AND SAME LOCATION). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/18/2023
Permit Application Status History
| Submitted | 2/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/21/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/25/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Plan Check Approved | 7/29/2022 | ALFRED RAMIREZ |
| Issued | 9/7/2022 | APPLICANT |
| Permit Finaled | 10/18/2023 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/27/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2022 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 5/28/2022 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 5/28/2022 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 7/27/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Jno Construction And Design Inc; Lic. No.: 1051923-B | 711 HUNTLEY DRIVE WEST HOLLYWOOD, CA 90069 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/12/2022 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | CLAYTON GRAHAM |
| Wood Frame | 8/8/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 8/29/2023 | Approved | BEN MOLSTAD |
| Drywall Nailing | 9/21/2023 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/11/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 10/11/2023 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 10/11/2023 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/18/2023 | Permit Finaled | STEPHANIE SWANSON |
| Smoke Detectors | 10/18/2023 | Approved | STEPHANIE SWANSON |