20525 W NORDHOFF ST 91311
Certificate Information: 20525 W NORDHOFF ST 91311
- Application / Permit
- 22016-20000-04439
- Plan Check / Job No.
- B22VN02314
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- ePLAN. NEW MECHANICAL ROOM ADDITION TO (E) WAREHOUSE AND OFFICE. NEW ROOFTOP SOLAR PV.
- Permit Issued
- Issued on 5/17/2022
- Issuing Office
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2022 | KEVIN MORALES |
| Corrections Issued | 2/16/2022 | KEVIN MORALES |
| Plan Check Approved | 5/13/2022 | KEVIN MORALES |
| Issued | 5/17/2022 | APPLICANT |
| CofO in Progress | 2/6/2026 | DEANDRE HOFFMAN |
| Permit Finaled | 2/10/2026 | JEFFREY DURAN |
| CofO Issued | 2/10/2026 | JEFFREY DURAN |
| Permit Finaled | 2/10/2026 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 4/28/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 4/28/2022 | MIGUEL GAMBOA |
| Metro Rail approval | Cleared | 5/10/2022 | KEVIN MORALES |
| Miscellaneous | Cleared | 5/13/2022 | WILLIAM JOHNS |
Contact Information
| Contractor | Tesla Inc; Lic. No.: 949283-B | 901 PAGE AVENUE FREMONT, CA 94538 |
| Engineer | Kim,, Yoo Jin; Lic. No.: NA5771 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 8/3/2022 | Conditional Approval | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Partial Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 9/15/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 9/21/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 9/22/2022 | Conditional Approval | JEFFREY FULTON |
| Pre-Inspection | 9/28/2022 | Corrections Issued | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 10/27/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 1/26/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 2/14/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 2/17/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Reinf. Masonry | 2/21/2023 | Conditional Approval | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 3/7/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 3/17/2023 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 4/5/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 4/26/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Pre-Inspection | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Reinforced Masonry Frame | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 6/12/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Pre-Inspection | 7/24/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 7/27/2024 | Off-Hour Fees Due | |
| Final | 12/19/2025 | OK to Issue CofO | RAFAEL CORTES |
| Footing/Foundation/Slab | 12/19/2025 | Approved | RAFAEL CORTES |
| Green Building Final | 12/19/2025 | Approved | RAFAEL CORTES |
| Green Building Rough | 12/19/2025 | Approved | RAFAEL CORTES |
| Reinforced Masonry Frame | 12/19/2025 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 12/19/2025 | Approved | RAFAEL CORTES |