6108 W 76TH ST 90045
Certificate Information: 6108 W 76TH ST 90045
- Application / Permit
- 22016-20000-04167
- Plan Check / Job No.
- B22VN02195
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO TO KITCHEN, LAUNDRY ROOM, AND TWO BATHROOMS. REMOVE AND REPLACE WINDOWS AND DOORS. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- Issued on 3/15/2022
Permit Application Status History
| Submitted | 2/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 2/20/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/15/2022 | JEROME MAGAT PALMA |
| Issued | 3/15/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/14/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Valdez Investments Inc; Lic. No.: 969738-B | 12839 FARNELL STREET BALDWIN PARK, CA 91706 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/7/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 4/7/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 4/21/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/27/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/27/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/27/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/27/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | BOBBY KEY |
| Wood Frame | 4/27/2022 | Approved | BOBBY KEY |
| Insulation | 5/3/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/3/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/16/2022 | Approved | BOBBY KEY |
| Gas Test | 7/1/2022 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 7/1/2022 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 7/12/2022 | Approved | JESUS RODRIGUEZ |
| Final | 9/19/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 9/19/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 9/19/2022 | Approved | BOBBY KEY |