17839-17841 W OSBORNE ST 91325

Certificate Information: 17839-17841 W OSBORNE ST 91325

Application / Permit
22016-20000-04122
Plan Check / Job No.
B22VN02173
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PART OF EXISTING SFD TO JADU (462 SQ.FT.)
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 CARLOS MONTES
Corrections Issued 2/18/2022 CARLOS MONTES
Building Plans Picked Up 4/7/2022 APPLICANT
Plan Check Approved 5/19/2022 CARLOS MONTES
Issued 5/24/2022 APPLICANT
CofO in Progress 1/19/2024 JAVIER RAMOS JR
Permit Finaled 1/30/2024 RUBEN SALAS
CofO Issued 1/30/2024 RUBEN SALAS
Permit Finaled 1/30/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/9/2022 LEE GUILBEAUX
Sewer availability Cleared 3/9/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/21/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/21/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/31/2023 Approved MICHEL ABAJAN
Drywall Nailing 9/6/2023 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Final 9/6/2023 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 9/6/2023 No Access for Inspection JAVIER RAMOS JR
Drywall Nailing 9/11/2023 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 9/11/2023 Approved DAVID ANDERSON
HVAC-Rough 9/11/2023 Corrections Issued DAVID ANDERSON
Drywall Nailing 9/19/2023 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 9/27/2023 Approved JAVIER RAMOS JR
HVAC-Rough 9/27/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/6/2023 Approved JAVIER RAMOS JR
Final 10/6/2023 Corrections Issued JAVIER RAMOS JR
Smoke Detectors 10/6/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 1/9/2024 Approved JAVIER RAMOS JR
Final 1/9/2024 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 1/9/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 1/9/2024 Approved JAVIER RAMOS JR