17839-17841 W OSBORNE ST 91325
Certificate Information: 17839-17841 W OSBORNE ST 91325
- Application / Permit
- 22016-20000-04122
- Plan Check / Job No.
- B22VN02173
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PART OF EXISTING SFD TO JADU (462 SQ.FT.)
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | CARLOS MONTES |
| Corrections Issued | 2/18/2022 | CARLOS MONTES |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| Plan Check Approved | 5/19/2022 | CARLOS MONTES |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 1/19/2024 | JAVIER RAMOS JR |
| Permit Finaled | 1/30/2024 | RUBEN SALAS |
| CofO Issued | 1/30/2024 | RUBEN SALAS |
| Permit Finaled | 1/30/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/9/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/21/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/31/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/6/2023 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/6/2023 | No Access for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/6/2023 | No Access for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 9/11/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/11/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/11/2023 | Corrections Issued | DAVID ANDERSON |
| Drywall Nailing | 9/19/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 9/27/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/27/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | JAVIER RAMOS JR |
| Final | 10/6/2023 | Corrections Issued | JAVIER RAMOS JR |
| Smoke Detectors | 10/6/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| Final | 1/9/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| HVAC-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/9/2024 | Approved | JAVIER RAMOS JR |