13225 1/2 W RAVEN ST 91342

Certificate Information: 13225 1/2 W RAVEN ST 91342

Application / Permit
22016-20000-04120
Plan Check / Job No.
B22VN02171
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Existing detached garage to be Converted to new A.D.U. per WFPP (FULLY SPRINKLERED)
Permit Issued
Issued on 11/9/2022
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2022 APPLICANT
Assigned to Plan Check Engineer 2/11/2022 JOE VO
Corrections Issued 2/12/2022 JOE VO
Plan Check Approved 7/28/2022 JOE VO
Issued 11/9/2022 APPLICANT
CofO in Progress 6/3/2024 KEVIN BERBERYAN
No Progress 7/12/2024 ROBERT GOLD
CofO in Progress 7/12/2024 ROBERT GOLD
Permit Finaled 8/5/2024 RUBEN SALAS
CofO Issued 8/5/2024 RUBEN SALAS
Permit Finaled 8/5/2024 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/21/2022 VASIL MIHALEV
Address approval Cleared 5/9/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/9/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/17/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 7/15/2022 KURT CORRAL
Construction near power lines Cleared 7/26/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/15/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/16/2023 Approved WILLIAM WREN
Footing/Foundation/Slab 8/16/2023 Approved WILLIAM WREN
PLUMBING-Rough 9/18/2023 Approved KEVIN BERBERYAN
Wood Frame 9/18/2023 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 11/22/2023 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 11/28/2023 Approved KEVIN BERBERYAN
HVAC-Rough 12/26/2023 Approved KEVIN BERBERYAN
Sewer 12/26/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 1/11/2024 Approved KEVIN BERBERYAN
Green Building Rough 1/11/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 1/29/2024 Approved MICHEL ABAJAN
Insulation 1/31/2024 Approved MICHEL ABAJAN
Drywall Nailing 2/12/2024 Approved THOMAS FINNILA
Shower Pan 3/7/2024 Approved KEVIN BERBERYAN
Final 5/10/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 5/10/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 5/10/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 5/17/2024 OK to Issue CofO KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 5/17/2024 Approved KEVIN BERBERYAN