13225 1/2 W RAVEN ST 91342
Certificate Information: 13225 1/2 W RAVEN ST 91342
- Application / Permit
- 22016-20000-04120
- Plan Check / Job No.
- B22VN02171
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Existing detached garage to be Converted to new A.D.U. per WFPP (FULLY SPRINKLERED)
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | JOE VO |
| Corrections Issued | 2/12/2022 | JOE VO |
| Plan Check Approved | 7/28/2022 | JOE VO |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 6/3/2024 | KEVIN BERBERYAN |
| No Progress | 7/12/2024 | ROBERT GOLD |
| CofO in Progress | 7/12/2024 | ROBERT GOLD |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
| CofO Issued | 8/5/2024 | RUBEN SALAS |
| Permit Finaled | 8/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/21/2022 | VASIL MIHALEV |
| Address approval | Cleared | 5/9/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/9/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 7/15/2022 | KURT CORRAL |
| Construction near power lines | Cleared | 7/26/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/15/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/16/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 8/16/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 9/18/2023 | Approved | KEVIN BERBERYAN |
| Wood Frame | 9/18/2023 | Corrections Issued | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/22/2023 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/28/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 12/26/2023 | Approved | KEVIN BERBERYAN |
| Sewer | 12/26/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/11/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 1/11/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/29/2024 | Approved | MICHEL ABAJAN |
| Insulation | 1/31/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 2/12/2024 | Approved | THOMAS FINNILA |
| Shower Pan | 3/7/2024 | Approved | KEVIN BERBERYAN |
| Final | 5/10/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 5/10/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 5/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 5/17/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 5/17/2024 | Approved | KEVIN BERBERYAN |