6530-6532 N SHOUP AVE 91307
Certificate Information: 6530-6532 N SHOUP AVE 91307
- Application / Permit
- 22016-20000-04113
- Plan Check / Job No.
- B22VN02167
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert Existing Bedroom and Living area within (E) SFD into new 2 Bedroom ADU (794 SF) per GCS 65852.2(e)(1)(A) with bathroom and kitchen.
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Current Status
- CofO Issued on 9/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2022 | JOE VO |
| Corrections Issued | 2/15/2022 | JOE VO |
| Plan Check Approved | 3/24/2022 | JOE VO |
| Issued | 3/24/2022 | APPLICANT |
| CofO in Progress | 8/30/2022 | TROY SANDERS |
| Permit Finaled | 9/28/2022 | JOHN JANSON |
| CofO Issued | 9/28/2022 | JOHN JANSON |
| Permit Finaled | 9/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/8/2022 | ROSE MARIE SMITH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/6/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 5/6/2022 | Approved | TROY SANDERS |
| Insulation | 5/6/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/6/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 5/6/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 5/12/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/29/2022 | Approved | TROY SANDERS |
| Final | 8/29/2022 | OK to Issue CofO | TROY SANDERS |
| HVAC-Final | 8/29/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 8/29/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/29/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/29/2022 | Approved | TROY SANDERS |