7833-7835 N HESPERIA AVE 91335

Certificate Information: 7833-7835 N HESPERIA AVE 91335

Application / Permit
22016-20000-04086
Plan Check / Job No.
B22VN02152
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 34' 4" X 18' 1" IRR.-SHAPE PORTION OF (E) SINGLE FAMILY DWELLING AND ATTACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 5/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2022 APPLICANT
Assigned to Plan Check Engineer 2/22/2022 SARKIS HARABEDIAN
Corrections Issued 2/24/2022 SARKIS HARABEDIAN
Plan Check Approved 4/7/2022 GURUNATH NESARAJAH
Issued 4/13/2022 APPLICANT
Building Plans Picked Up 4/14/2022 APPLICANT
CofO in Progress 5/23/2023 JEFFREY BULL
Permit Finaled 5/23/2023 JOHN JANSON
CofO Issued 5/23/2023 JOHN JANSON
Permit Finaled 5/23/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/28/2022 CARLOS AGUILERA
Sewer availability Cleared 3/29/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/12/2022 Not Ready for Inspection JEFFREY BULL
Pre-Inspection 8/12/2022 Approved JEFFREY BULL
Deputy Drilled-In Anchors 8/19/2022 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 8/26/2022 Approved SEAN HAUPT
Wood Frame 11/28/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 1/11/2023 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 1/11/2023 Corrections Issued KRISTEN CAUSEY
Interior/Exterior Lathing 1/18/2023 Approved JEFFREY BULL
PLUMBING-Rough 1/18/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 2/9/2023 Approved JEFFREY BULL
HVAC-Rough 2/9/2023 Approved JEFFREY BULL
Insulation 2/17/2023 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 2/22/2023 Approved JEFFREY BULL
Green Building Rough 2/22/2023 Approved JEFFREY BULL
Insulation 2/22/2023 Approved JEFFREY BULL
Drywall Nailing 3/13/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Approved JEFFREY BULL
Service/Power Release 3/13/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 4/7/2023 Approved JEFFREY BULL
ELECTRICAL-Final 5/4/2023 Approved JEFFREY BULL
Final 5/4/2023 Not Ready for Inspection JEFFREY BULL
Green Building Final 5/4/2023 Approved JEFFREY BULL
HVAC-Final 5/4/2023 Approved JEFFREY BULL
PLUMBING-Final 5/4/2023 Approved JEFFREY BULL
Smoke Detectors 5/4/2023 Approved JEFFREY BULL
Final 5/23/2023 OK to Issue CofO JEFFREY BULL