14115-14117 W PIERCE ST 91331
Certificate Information: 14115-14117 W PIERCE ST 91331
- Application / Permit
- 22016-20000-04078
- Plan Check / Job No.
- B22VN02139
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C).
- Permit Issued
- Issued on 6/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | SERGIO MUNIZ |
| Corrections Issued | 2/20/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 5/11/2022 | SERGIO MUNIZ |
| Plan Check Approved | 5/24/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Issued | 6/3/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | MICHEL ABAJAN |
| CofO Issued | 7/13/2023 | RONALD MYRICK |
| Permit Finaled | 7/13/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 4/12/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/12/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/28/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 10/28/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/16/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/16/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/16/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 12/16/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/16/2022 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Rough | 12/27/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 12/27/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 12/27/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Insulation | 1/10/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/10/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 1/10/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/18/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/18/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/12/2023 | Approved | MICHEL ABAJAN |
| Final | 7/12/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 7/12/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/12/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/12/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/12/2023 | Approved | MICHEL ABAJAN |