14825 W STRATHERN ST 91402
Certificate Information: 14825 W STRATHERN ST 91402
- Application / Permit
- 22016-20000-03966
- Plan Check / Job No.
- B22VN02085
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT) PER CA Govt. Code 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 2/20/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 4/22/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 6/14/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 7/12/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Plan Check Approved | 8/11/2022 | JEROME MAGAT PALMA |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 11/6/2023 | DAVID MATSON |
| Permit Finaled | 11/18/2023 | RUBEN SALAS |
| CofO Issued | 11/18/2023 | RUBEN SALAS |
| Permit Finaled | 11/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/25/2022 | RIDWAN HARDY |
| Address approval | Cleared | 7/28/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 7/28/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/22/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 12/22/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/17/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/17/2023 | Approved | GREGG CUMMINGS |
| Gas Test | 2/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 2/17/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/19/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/19/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/19/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/28/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/28/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Sewer | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 4/28/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/1/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/1/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Gas Test | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 5/1/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/1/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/12/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/12/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 5/12/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/31/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | MISAEL ESPARZA |
| Final | 7/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 7/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 7/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 7/27/2023 | OK to Issue CofO | DAVID MATSON |
| Green Building Final | 7/27/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 7/27/2023 | Approved | DAVID MATSON |