5012 N NAGLE AVE 91423

Certificate Information: 5012 N NAGLE AVE 91423

Application / Permit
22016-20000-03798
Plan Check / Job No.
B22VN01990
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (e) sfd. Convert portion of (e) sfd into a new 3/4 bthrm and new half bthrm. Remove portion of wall between kitchen and living rm. Relocate laundry and entry door. All work per engineer.
Permit Issued
Issued on 3/7/2022
Issuing Office
Current Status
Permit Finaled on 1/6/2023

Permit Application Status History

Submitted 2/8/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2022 ANGELICA DAVE
Corrections Issued 2/9/2022 ANGELICA DAVE
Plan Check Approved 3/7/2022 ANGELICA MARTINEZ
Issued 3/7/2022 APPLICANT
Building Plans Picked Up 3/8/2022 APPLICANT
Permit Finaled 1/4/2023 MISAEL ESPARZA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Or - 5 General Contractor Corp; Lic. No.: 861315-B 23349 CANZONET ST      WOODLAND HILLS, CA 91367
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 5/24/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 7/26/2022 Corrections Issued MISAEL ESPARZA
Gas Test 7/26/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 7/26/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 7/26/2022 Partial Approval MISAEL ESPARZA
Wood Frame 7/26/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/5/2022 Corrections Issued DEANDRE HOFFMAN
ELECTRICAL-Rough 8/5/2022 Approved DEANDRE HOFFMAN
HVAC-Rough 8/5/2022 Approved DEANDRE HOFFMAN
PLUMBING-Rough 8/5/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 8/17/2022 Partial Approval MISAEL ESPARZA
Shower Pan 8/17/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/17/2022 Corrections Issued MISAEL ESPARZA
Insulation 8/24/2022 Conditional Approval MISAEL ESPARZA
Drywall Nailing 9/7/2022 Approved ALAN MORELOS
Shower Pan 9/7/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 10/11/2022 Approved DEANDRE HOFFMAN
Final 12/28/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 12/28/2022 Corrections Issued MISAEL ESPARZA
Final 1/4/2023 Permit Finaled MISAEL ESPARZA
Smoke Detectors 1/4/2023 Approved MISAEL ESPARZA