10954 W CROCKETT ST 91352
Certificate Information: 10954 W CROCKETT ST 91352
- Application / Permit
- 22016-20000-03731
- Plan Check / Job No.
- B22VN01962
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Converting existing garage/storage into accessory dwelling unit per ordinance. All work per type V sheet.
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/18/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/17/2022 | FARSHAD ALIMOHAMADI |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | MATTHEW NELSON |
| CofO Issued | 1/9/2023 | RONALD MYRICK |
| Permit Finaled | 1/9/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/14/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Sire Energy Inc; Lic. No.: 1027415-B | 21054 SHERMAN WAY #325 CANOGA PARK, CA 91303 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 7/21/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 7/26/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 7/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 8/2/2022 | No Result Entered | ADRIAN GAUTHIER |
| Footing/Foundation/Slab | 8/2/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/2/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 8/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 8/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 8/31/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/7/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 9/7/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/7/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 9/7/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 9/7/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/14/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Approved | WILLIAM WREN |
| Insulation | 9/14/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/14/2022 | Approved | WILLIAM WREN |
| MERV13>=Rough | 9/14/2022 | Approved | WILLIAM WREN |
| Shower Pan | 9/14/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/19/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/13/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 12/13/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/13/2022 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 12/13/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/13/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Service/Power Release | 12/13/2022 | Corrections Issued | MATTHEW NELSON |
| Smoke Detectors | 12/13/2022 | Approved | MATTHEW NELSON |
| Pre-Inspection | 12/16/2022 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 12/22/2022 | Approved | MATTHEW NELSON |
| Final | 12/22/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 12/22/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/22/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 12/22/2022 | Approved | MATTHEW NELSON |