4236 N VERDUGO ROAD 90065
Certificate Information: 4236 N VERDUGO ROAD 90065
- Application / Permit
- 22016-20000-03683
- Plan Check / Job No.
- B22VN01937
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-4" X 20'-4" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO Issued on 12/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/21/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/1/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 11/28/2022 | CRAIG VAUGHAN |
| CofO in Progress | 11/28/2022 | CRAIG VAUGHAN |
| CofO Issued | 12/12/2022 | DEROLD HAUFF |
| Permit Finaled | 12/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/26/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | CHRISTOPHER ROCHA |
| Tenant Habitability Plan | Cleared | 3/1/2022 | MICHAEL SOTO |
| Supp. Use District POD/CDO/TDO | Cleared | 3/14/2022 | NASHYA JENSEN |
| ZI | Cleared | 3/14/2022 | NASHYA JENSEN |
| Construction near power lines | Cleared | 4/19/2022 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 5/1/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/2/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 8/2/2022 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 8/2/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/2/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/5/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/5/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/5/2022 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 8/10/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/16/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/16/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 8/16/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/28/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 9/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 9/28/2022 | Approved | CRAIG VAUGHAN |
| Green Building Final | 9/28/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 9/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| MERV13>=Final | 9/28/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 9/28/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 9/28/2022 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Final | 10/6/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 10/6/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 10/6/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 10/6/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 10/6/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/7/2022 | Approved | CRAIG VAUGHAN |
| Final | 11/7/2022 | Conditional Approval | CRAIG VAUGHAN |
| Service/Power Release | 11/7/2022 | Approved | CRAIG VAUGHAN |
| Final | 11/15/2022 | OK to Issue CofO | CRAIG VAUGHAN |