10027 N LEONA AVE 91042

Certificate Information: 10027 N LEONA AVE 91042

Application / Permit
22016-20000-03433
Plan Check / Job No.
B22VN01805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. CONVERT (E) GARAGE TO ADU WITH ADDITION
Permit Issued
Issued on 11/30/2022
Issuing Office
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 CRYSTEL MAALOUF
Corrections Issued 3/25/2022 CRYSTEL MAALOUF
Quality Review Completed 3/30/2022 SAI KHUM
Applicant returned to address corrections 8/1/2022 CRYSTEL MAALOUF
Plan Check Approved 8/24/2022 CRYSTEL MAALOUF
Issued 11/30/2022 APPLICANT
CofO in Progress 7/18/2023 MATTHEW NELSON
Permit Finaled 7/19/2023 MICHAEL SMITH
CofO Issued 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/25/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/2/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 6/22/2022 KIRK LINKLATER
Low Impact Development Cleared 7/11/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 7/15/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 8/24/2022 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/16/2022 Approved WILLIAM WREN
Footing/Foundation/Slab 12/16/2022 Approved WILLIAM WREN
PLUMBING-Rough 12/16/2022 Partial Approval WILLIAM WREN
HVAC-Rough 2/9/2023 Corrections Issued WILLIAM WREN
Sewer 2/9/2023 Approved WILLIAM WREN
Wood Frame 2/9/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/16/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 2/16/2023 Corrections Issued WILLIAM WREN
Gas Test 2/16/2023 Partial Approval WILLIAM WREN
Green Building Rough 2/16/2023 Approved WILLIAM WREN
HVAC-Rough 2/16/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 2/16/2023 Approved WILLIAM WREN
Underground Mechanical 2/16/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 2/23/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved WILLIAM WREN
HVAC-Rough 2/23/2023 Approved WILLIAM WREN
PLUMBING-Rough 2/23/2023 Approved WILLIAM WREN
Insulation 2/28/2023 Corrections Issued WILLIAM WREN
Insulation 3/8/2023 Approved WILLIAM WREN
Shower Pan 3/8/2023 Approved WILLIAM WREN
Drywall Nailing 3/14/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 3/14/2023 Approved WILLIAM WREN
Final 6/29/2023 Corrections Issued WILLIAM WREN
Green Building Final 6/29/2023 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 6/29/2023 Approved WILLIAM WREN
Final 7/17/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 7/17/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/17/2023 SGSOV Approved MATTHEW NELSON