10928 N ZELZAH AVE 91344

Certificate Information: 10928 N ZELZAH AVE 91344

Application / Permit
22016-20000-03345
Plan Check / Job No.
B22VN01757
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN* Convert Garage to ADU & Addition per ordinance LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/3/2022
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 MICHAEL LOPEZ
Corrections Issued 2/17/2022 MICHAEL LOPEZ
Applicant returned to address corrections 8/8/2022 MICHAEL LOPEZ
Applicant returned to address corrections 8/30/2022 MICHAEL LOPEZ
Applicant returned to address corrections 10/28/2022 HANS SANTIAGO
Plan Check Approved 11/1/2022 ANDREW SANTIAGO
Issued 11/3/2022 APPLICANT
CofO in Progress 6/10/2024 STEVEN BACK
Permit Finaled 7/10/2024 JOHN JANSON
CofO Issued 7/10/2024 JOHN JANSON
Permit Finaled 7/10/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/31/2022 CARLOS AGUILERA
Address approval Cleared 4/1/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/2/2022 CARLOS AGUILERA
Sewer availability Cleared 4/5/2022 CARLOS AGUILERA

Contact Information

Architect Hefner,, Charles David; Lic. No.: NA23963       ,
Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2023 Approved STEVEN BACK
Footing/Foundation/Slab 9/15/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 9/21/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 9/21/2023 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 9/22/2023 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 10/17/2023 Approved STEVEN BACK
ELECTRICAL-Rough 10/17/2023 Approved STEVEN BACK
Green Building Rough 10/17/2023 Approved STEVEN BACK
HVAC-Rough 10/17/2023 Approved STEVEN BACK
Interior/Exterior Lathing 10/17/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 10/17/2023 Approved STEVEN BACK
Insulation 10/26/2023 Approved HENRY KIM
Drywall Nailing 10/30/2023 Approved STEVEN BACK
Interior/Exterior Lathing 10/30/2023 Approved STEVEN BACK
Shower Pan 10/30/2023 Approved STEVEN BACK
Final 3/18/2024 Corrections Issued STEVEN BACK
Green Building Final 3/18/2024 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Not Ready STEVEN BACK
Smoke Detectors 3/18/2024 Approved STEVEN BACK
Final 5/28/2024 Partial Approval GEVORK IPCHYAN
Green Building Final 5/28/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved GEVORK IPCHYAN
Final 6/10/2024 OK to Issue CofO STEVEN BACK
Service/Power Release 6/10/2024 Approved STEVEN BACK