10928 N ZELZAH AVE 91344
Certificate Information: 10928 N ZELZAH AVE 91344
- Application / Permit
- 22016-20000-03345
- Plan Check / Job No.
- B22VN01757
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN* Convert Garage to ADU & Addition per ordinance LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | MICHAEL LOPEZ |
| Corrections Issued | 2/17/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/8/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/30/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/28/2022 | HANS SANTIAGO |
| Plan Check Approved | 11/1/2022 | ANDREW SANTIAGO |
| Issued | 11/3/2022 | APPLICANT |
| CofO in Progress | 6/10/2024 | STEVEN BACK |
| Permit Finaled | 7/10/2024 | JOHN JANSON |
| CofO Issued | 7/10/2024 | JOHN JANSON |
| Permit Finaled | 7/10/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/31/2022 | CARLOS AGUILERA |
| Address approval | Cleared | 4/1/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/5/2022 | CARLOS AGUILERA |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/15/2023 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 9/15/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/21/2023 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/21/2023 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/22/2023 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/17/2023 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 10/17/2023 | Approved | STEVEN BACK |
| Green Building Rough | 10/17/2023 | Approved | STEVEN BACK |
| HVAC-Rough | 10/17/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/17/2023 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 10/17/2023 | Approved | STEVEN BACK |
| Insulation | 10/26/2023 | Approved | HENRY KIM |
| Drywall Nailing | 10/30/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/30/2023 | Approved | STEVEN BACK |
| Shower Pan | 10/30/2023 | Approved | STEVEN BACK |
| Final | 3/18/2024 | Corrections Issued | STEVEN BACK |
| Green Building Final | 3/18/2024 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 3/18/2024 | Approved | STEVEN BACK |
| Final | 5/28/2024 | Partial Approval | GEVORK IPCHYAN |
| Green Building Final | 5/28/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Final | 6/10/2024 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 6/10/2024 | Approved | STEVEN BACK |