11201 W ACAMA ST 91602

Certificate Information: 11201 W ACAMA ST 91602

Application / Permit
22016-20000-03218
Plan Check / Job No.
B22VN01680
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSET THE (E) 57 SQ. FT. BREEZEWAY TO CREATE A NEW LAUNDRY ROOM. REMODEL THE (E) KITCHEN AND POWDER ROOM.
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/11/2022 JESSE ARELLANO
Corrections Issued 2/11/2022 JESSE ARELLANO
Applicant returned to address corrections 2/26/2022 JESSE ARELLANO
Issued 3/1/2022 APPLICANT
Building Plans Picked Up 3/16/2022 APPLICANT
CofO in Progress 9/22/2022 DEANDRE HOFFMAN
CofO in Progress 9/22/2022 DEANDRE HOFFMAN
CofO Issued 9/22/2022 MICHAEL SMITH
Permit Finaled 9/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 2/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/16/2022 CARLOS AGUILERA
Green Code Cleared 2/28/2022 JESSE ARELLANO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Ha My Design Inc; Lic. No.: 999603-B 6700 FALLBROOK AVE #235      WEST HILLS, CA 91307

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/5/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 4/11/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 4/21/2022 Corrections Issued DAVID MATSON
ELECTRICAL-Rough 4/21/2022 Approved DAVID MATSON
Green Building Rough 4/21/2022 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 4/21/2022 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 4/26/2022 Approved WILLIAM WREN
Green Building Rough 4/26/2022 Approved WILLIAM WREN
PLUMBING-Rough 4/26/2022 Approved WILLIAM WREN
Insulation 4/29/2022 Conditional Approval THOMAS FINNILA
Drywall Nailing 5/3/2022 Approved DAVID MATSON
Gas Test 5/3/2022 Approved DAVID MATSON
Final 9/7/2022 Partial Approval DEANDRE HOFFMAN
Green Building Final 9/7/2022 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 9/7/2022 Approved DEANDRE HOFFMAN
Final 9/16/2022 OK to Issue CofO DEANDRE HOFFMAN