6810 N LINDLEY AVE 91335
Certificate Information: 6810 N LINDLEY AVE 91335
- Application / Permit
- 22016-20000-02883
- Plan Check / Job No.
- B22VN01470
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 20'-4" x 18'-6" GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A.33 (c) & (d). ALL WORK PER WFPP
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Current Status
- CofO Issued on 8/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 2/13/2022 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 5/10/2022 | HAYATO TSUCHIYA |
| Issued | 5/27/2022 | APPLICANT |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| CofO in Progress | 8/12/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 8/20/2025 | JOHN JANSON |
| CofO Issued | 8/20/2025 | JOHN JANSON |
| Permit Finaled | 8/20/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/22/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 4/13/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/3/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Pre-Inspection | 2/4/2025 | Partial Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/7/2025 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 2/10/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | JUAN ALVARADO |
| Pre-Inspection | 3/12/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Insulation | 4/15/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | JUAN ALVARADO |
| BUILDING-Rough-Frame | 5/5/2025 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Rough | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 5/5/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 5/8/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 5/15/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 5/22/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 5/22/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Rough | 7/7/2025 | No Access for Inspection | KRISTEN CAUSEY |
| Underground Mechanical | 7/9/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| Final | 7/24/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 7/24/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 7/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 8/6/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2025 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 8/6/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 8/11/2025 | Approved | ARUTYUN MADATYAN |
| Final | 8/11/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 8/11/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 8/11/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 8/11/2025 | Approved | ARUTYUN MADATYAN |