17440-17442 W MAYALL ST 91325

Certificate Information: 17440-17442 W MAYALL ST 91325

Application / Permit
22016-20000-02837
Plan Check / Job No.
B22VN01448
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ATTACHED ADU PER STATE LAW
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2022 APPLICANT
Assigned to Plan Check Engineer 2/1/2022 CARLOS MONTES
Corrections Issued 2/1/2022 CARLOS MONTES
Plan Check Approved 2/11/2022 CARLOS MONTES
Issued 2/17/2022 APPLICANT
CofO in Progress 3/10/2023 JAVIER RAMOS JR
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/4/2022 AMIR KASHFI
Sewer availability Cleared 2/4/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 2/11/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/30/2022 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 4/1/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 4/7/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/23/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 6/23/2022 Not Ready for Inspection JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 6/23/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 9/19/2022 Approved JAVIER RAMOS JR
Green Building Rough 9/19/2022 Approved JAVIER RAMOS JR
Insulation 9/19/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/19/2022 Approved JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 9/19/2022 Approved JAVIER RAMOS JR
Drywall Nailing 9/29/2022 Approved JAVIER RAMOS JR
Final 12/7/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/7/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/7/2022 Approved JAVIER RAMOS JR
Final 2/24/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 2/24/2023 Approved JAVIER RAMOS JR
Sewer 2/24/2023 Approved JAVIER RAMOS JR
Verify Rec and Parks Fee Memo 3/1/2023 Approved DAVID MATSON
Final 3/8/2023 OK to Issue CofO JAVIER RAMOS JR