11529-11531 N DE CELIS PL 91344

Certificate Information: 11529-11531 N DE CELIS PL 91344

Application / Permit
22016-20000-02752
Plan Check / Job No.
B22VN01425
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) 21' x 21'4" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 JEFFREY TANGONAN
Corrections Issued 2/10/2022 JEFFREY TANGONAN
Applicant returned to address corrections 3/3/2022 JEFFREY TANGONAN
Applicant returned to address corrections 3/17/2022 JEFFREY TANGONAN
Plan Check Approved 3/24/2022 JEFFREY TANGONAN
Building Plans Picked Up 3/25/2022 APPLICANT
Issued 4/21/2022 APPLICANT
CofO in Progress 7/24/2023 ROBERT GOLD
Permit Finaled 8/23/2023 RUBEN SALAS
CofO Issued 8/23/2023 RUBEN SALAS
Permit Finaled 8/23/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/24/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/24/2022 CARLOS AGUILERA
Sewer availability Cleared 2/24/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/18/2022 Corrections Issued MICHAEL TEMPLE
Deputy Drilled-In Anchors 5/20/2022 Approved DEANDRE HOFFMAN
Footing/Foundation/Slab 5/20/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 5/23/2022 Approved MICHAEL TEMPLE
PLUMBING-Rough 7/29/2022 Partial Approval DEANDRE HOFFMAN
Pre-Inspection 9/14/2022 Approved JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 9/14/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 10/17/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 10/17/2022 Approved JAVIER RAMOS JR
Green Building Rough 10/17/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 10/17/2022 Approved JAVIER RAMOS JR
Insulation 11/18/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 11/18/2022 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/1/2022 Approved JAVIER RAMOS JR
Green Building Rough 12/1/2022 Approved JAVIER RAMOS JR
Insulation 12/1/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 12/1/2022 Partial Approval JAVIER RAMOS JR
Drywall Nailing 1/5/2023 Corrections Issued RAUL OLAGI
Insulation 1/5/2023 Approved RAUL OLAGI
Shower Pan 1/5/2023 Corrections Issued RAUL OLAGI
Drywall Nailing 1/13/2023 Approved JAVIER RAMOS JR
Shower Pan 1/13/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/14/2023 Approved JAVIER RAMOS JR
Final 4/14/2023 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 4/14/2023 Approved JAVIER RAMOS JR
HVAC-Final 4/14/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 4/14/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 4/14/2023 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 4/14/2023 Approved JAVIER RAMOS JR
Final 7/7/2023 OK to Issue CofO ROBERT GOLD