11529-11531 N DE CELIS PL 91344
Certificate Information: 11529-11531 N DE CELIS PL 91344
- Application / Permit
- 22016-20000-02752
- Plan Check / Job No.
- B22VN01425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 21' x 21'4" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 8/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | JEFFREY TANGONAN |
| Corrections Issued | 2/10/2022 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 3/3/2022 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 3/17/2022 | JEFFREY TANGONAN |
| Plan Check Approved | 3/24/2022 | JEFFREY TANGONAN |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 7/24/2023 | ROBERT GOLD |
| Permit Finaled | 8/23/2023 | RUBEN SALAS |
| CofO Issued | 8/23/2023 | RUBEN SALAS |
| Permit Finaled | 8/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/24/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2022 | Corrections Issued | MICHAEL TEMPLE |
| Deputy Drilled-In Anchors | 5/20/2022 | Approved | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 5/20/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 5/23/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 7/29/2022 | Partial Approval | DEANDRE HOFFMAN |
| Pre-Inspection | 9/14/2022 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 9/14/2022 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/17/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/17/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 10/17/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 11/18/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/18/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 12/1/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 12/1/2022 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/1/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 1/5/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 1/5/2023 | Approved | RAUL OLAGI |
| Shower Pan | 1/5/2023 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 1/13/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 1/13/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/14/2023 | Approved | JAVIER RAMOS JR |
| Final | 4/14/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 4/14/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/14/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 4/14/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/14/2023 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 4/14/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 4/14/2023 | Approved | JAVIER RAMOS JR |
| Final | 7/7/2023 | OK to Issue CofO | ROBERT GOLD |