5926 N VARNA AVE 91401
Certificate Information: 5926 N VARNA AVE 91401
- Application / Permit
- 22016-20000-02578
- Plan Check / Job No.
- B22VN01311
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED STORAGE AND GARAGE TO ADU, 942 SQFT PER CA GOVT CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/13/2023
- Issuing Office
- Valley
- Current Status
- Issued on 6/13/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | PETER MOSESIAN |
| Corrections Issued | 2/20/2022 | PETER MOSESIAN |
| Quality Review Completed | 2/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| Applicant returned to address corrections | 9/9/2022 | PETER MOSESIAN |
| Plan Check Approved | 12/14/2022 | PETER MOSESIAN |
| Issued | 6/13/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 12/5/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/26/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 7/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 7/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 7/26/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 7/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 7/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 7/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 7/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Deputy Drilled-In Anchors | 7/28/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/7/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 8/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 8/7/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 8/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 8/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| METHANE-Rough | 8/7/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 8/7/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/23/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 8/23/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 8/23/2023 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 8/23/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 8/23/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 10/11/2023 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 10/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/19/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 10/19/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 10/24/2023 | Approved | KIRK SANDERS |
| Insulation | 10/24/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 10/24/2023 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 10/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/1/2023 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Approved | CHRISTOPHER ROJAS |