5926 N VARNA AVE 91401

Certificate Information: 5926 N VARNA AVE 91401

Application / Permit
22016-20000-02578
Plan Check / Job No.
B22VN01311
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED STORAGE AND GARAGE TO ADU, 942 SQFT PER CA GOVT CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 6/13/2023
Issuing Office
Valley
Current Status
Issued on 6/13/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 PETER MOSESIAN
Corrections Issued 2/20/2022 PETER MOSESIAN
Quality Review Completed 2/24/2022 OMID HEDAYAT
Building Plans Picked Up 3/3/2022 APPLICANT
Applicant returned to address corrections 9/9/2022 PETER MOSESIAN
Plan Check Approved 12/14/2022 PETER MOSESIAN
Issued 6/13/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/14/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 3/14/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 12/5/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/26/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 7/26/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 7/26/2023 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 7/26/2023 Corrections Issued KIRK SANDERS
HVAC-Final 7/26/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 7/26/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 7/26/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 7/26/2023 Not Ready for Inspection KIRK SANDERS
Deputy Drilled-In Anchors 7/28/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/7/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 8/7/2023 Not Ready for Inspection KIRK SANDERS
Footing/Foundation/Slab 8/7/2023 Approved KIRK SANDERS
Green Building Rough 8/7/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 8/7/2023 Not Ready for Inspection KIRK SANDERS
METHANE-Rough 8/7/2023 Approved KIRK SANDERS
PLUMBING-Rough 8/7/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 8/23/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 8/23/2023 Corrections Issued KIRK SANDERS
Green Building Rough 8/23/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 8/23/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 8/23/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 10/11/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 10/11/2023 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 10/11/2023 Corrections Issued CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 10/11/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/19/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 10/19/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/24/2023 Partial Approval KIRK SANDERS
Green Building Rough 10/24/2023 Approved KIRK SANDERS
Insulation 10/24/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 10/24/2023 Partial Approval KIRK SANDERS
Drywall Nailing 10/30/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/1/2023 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Approved CHRISTOPHER ROJAS