2035 S RIMPAU BLVD 90016

Certificate Information: 2035 S RIMPAU BLVD 90016

Application / Permit
22016-20000-02079
Plan Check / Job No.
B22VN01095
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 25' 7" X 23' 3" IRR.-SHAPE DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 3/30/2022
Issuing Office
Current Status
CofO Issued on 11/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 GURUNATH NESARAJAH
Corrections Issued 2/4/2022 GURUNATH NESARAJAH
Plan Check Approved 3/29/2022 GURUNATH NESARAJAH
Issued 3/30/2022 APPLICANT
Building Plans Picked Up 4/1/2022 APPLICANT
CofO in Progress 11/5/2025 MARTIN TAVITIAN
Permit Finaled 11/7/2025 ERNESTO CORRAL
CofO Issued 11/7/2025 ERNESTO CORRAL
Permit Finaled 11/7/2025 ERNESTO CORRAL

Permit Application Clearance Information

Hold Cleared 2/7/2022 JASON SHEETS
Address approval Cleared 2/16/2022 WALLIE JONG
Sewer availability Cleared 2/16/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/17/2022 WALLIE JONG
Construction near power lines Cleared 3/1/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/13/2024 Partial Approval MARTIN TAVITIAN
Green Building Rough 9/10/2024 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 9/10/2024 Not Ready for Inspection MARTIN TAVITIAN
Interior/Exterior Lathing 9/18/2024 Partial Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 10/3/2024 Not Ready for Inspection MARTIN TAVITIAN
Green Building Rough 10/8/2024 Approved MARTIN TAVITIAN
Insulation 10/8/2024 Approved MARTIN TAVITIAN
Wood Frame 10/8/2024 Approved MARTIN TAVITIAN
Drywall Nailing 10/10/2024 Partial Approval CHRISTOPHER BLACKWOOD
Interior/Exterior Lathing 10/10/2024 Partial Approval CHRISTOPHER BLACKWOOD
Final 10/23/2025 OK to Issue CofO MARTIN TAVITIAN
Green Building Final 10/23/2025 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 10/23/2025 Approved MARTIN TAVITIAN