14201 W NORDHOFF ST 91402
Certificate Information: 14201 W NORDHOFF ST 91402
- Application / Permit
- 22016-20000-01637
- Plan Check / Job No.
- B22VN00827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW 13'4" X 26'8" COVERED TRASH ENCLOSURE FOR APARTMENT BUILDINGS, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | RARES BODEA |
| Corrections Issued | 1/31/2022 | RARES BODEA |
| Quality Review Completed | 2/3/2022 | STEVEN KIM |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 2/10/2022 | APPLICANT |
| Applicant returned to address corrections | 3/15/2022 | RARES BODEA |
| Applicant returned to address corrections | 4/21/2022 | RARES BODEA |
| Plan Check Approved | 5/16/2022 | RARES BODEA |
| Plan Check Approved | 5/16/2022 | RARES BODEA |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 8/5/2022 | ANDREW DORSO |
| CofO Issued | 8/5/2022 | JEFFREY DURAN |
| Permit Finaled | 8/5/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/8/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | JOSE DUARTE-DIAZ |
| DAS Clearance | Cleared | 3/29/2022 | NORLITO MEDRANO |
| Tract Map conditions | Cleared | 3/29/2022 | STEVEN WECHSLER |
| ZA Case | Cleared | 3/29/2022 | STEVEN WECHSLER |
Contact Information
| Contractor | Paragon Construction Company Llc; Lic. No.: 1072485-B | 2656 E DENIM TRL SAN TAN VALLEY, AZ 85143 |
| Engineer | Labib,, Youhanna T.; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Partial Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/25/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 6/14/2022 | Partial Inspection | ANDREW DORSO |
| Final | 6/21/2022 | Corrections Issued | ANDREW DORSO |
| Masonry Wall/Backfill | 6/21/2022 | Approved | ANDREW DORSO |
| Drywall Nailing | 8/5/2022 | Approved | ANDREW DORSO |
| Final | 8/5/2022 | OK to Issue CofO | ANDREW DORSO |
| Footing/Foundation/Slab | 8/5/2022 | Approved | ANDREW DORSO |
| Green Building Final | 8/5/2022 | Approved | ANDREW DORSO |
| Green Building Rough | 8/5/2022 | Approved | ANDREW DORSO |
| Reinforced Concrete Frame | 8/5/2022 | Approved | ANDREW DORSO |
| Reinforced Masonry Frame | 8/5/2022 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Not Required | ANDREW DORSO |
| Smoke Detectors | 8/5/2022 | Approved | ANDREW DORSO |
| Verify Sprinkler Sign Off | 8/5/2022 | Approved | ANDREW DORSO |
| Wood Frame | 8/5/2022 | Approved | ANDREW DORSO |