18730-18732 W ROXBURGH PL 91326

Certificate Information: 18730-18732 W ROXBURGH PL 91326

Application / Permit
22016-20000-01502
Plan Check / Job No.
B22VN00767
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12'-10" X 23'-4" 2ND FLOOR ADDITION & CONVERT THE (E) ATTACHED GARAGE AND DECK ABOVE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)and (e).
Permit Issued
Issued on 7/21/2022
Issuing Office
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 SERGIO MUNIZ
Corrections Issued 1/30/2022 SERGIO MUNIZ
Applicant returned to address corrections 5/20/2022 SERGIO MUNIZ
Applicant returned to address corrections 5/26/2022 SERGIO MUNIZ
Plan Check Approved 6/29/2022 SERGIO MUNIZ
Building Plans Picked Up 7/13/2022 APPLICANT
Issued 7/21/2022 APPLICANT
CofO in Progress 4/26/2023 STEVEN BACK
Permit Finaled 4/27/2023 JOHN JANSON
CofO Issued 4/27/2023 JOHN JANSON
Permit Finaled 4/27/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/8/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/8/2022 CARLOS AGUILERA
Sewer availability Cleared 3/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/17/2022 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 8/17/2022 Approved DAVID SCANTLIN
Green Building Rough 8/17/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 8/17/2022 Partial Approval DAVID SCANTLIN
METHANE-Rough 8/17/2022 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 8/17/2022 Partial Approval DAVID SCANTLIN
Pre-Inspection 8/17/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 9/21/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 9/30/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Approved SEAN WIRCH
Wood Frame 10/24/2022 Not Ready for Inspection SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved SEAN WIRCH
Green Building Rough 10/31/2022 Not Ready for Inspection SEAN WIRCH
Insulation 10/31/2022 Partial Approval SEAN WIRCH
METHANE-Rough 10/31/2022 Not Ready for Inspection SEAN WIRCH
Insulation 11/14/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 11/14/2022 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 1/9/2023 Corrections Issued STEVEN BACK
Green Building Rough 1/9/2023 Approved STEVEN BACK
Interior/Exterior Lathing 1/9/2023 Approved STEVEN BACK
METHANE-Rough 1/9/2023 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 1/10/2023 Approved SEAN WIRCH
METHANE-Rough 1/10/2023 Approved SEAN WIRCH
Rough-Elec/Plmb/HVAC 1/10/2023 Approved SEAN WIRCH
Drywall Nailing 1/11/2023 Approved STEVEN BACK
Final 3/22/2023 Corrections Issued SEAN HAUPT
Green Building Final 3/22/2023 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 3/22/2023 Approved SEAN HAUPT
Final 4/26/2023 OK to Issue CofO STEVEN BACK
Green Building Final 4/26/2023 Approved STEVEN BACK