8149 N HINDS AVE 91605

Certificate Information: 8149 N HINDS AVE 91605

Application / Permit
22016-20000-01424
Plan Check / Job No.
B22VN00687
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 3/14/2022
Issuing Office
Current Status
CofO Issued on 4/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2022 APPLICANT
Assigned to Plan Check Engineer 2/7/2022 CARLOS MONTES
Corrections Issued 2/8/2022 CARLOS MONTES
Plan Check Approved 3/12/2022 CARLOS MONTES
Issued 3/14/2022 APPLICANT
CofO in Progress 3/14/2023 MATTHEW NELSON
CofO Issued 4/5/2023 DANIEL ORRANTE
Permit Finaled 4/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/17/2022 CARLOS AGUILERA
Clean Up Green Up Cleared 2/17/2022 LAUREN PADICK
Sewer availability Cleared 2/17/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 3/22/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 3/24/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 3/25/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Pre-Inspection 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 11/22/2022 Not Ready for Inspection MATTHEW NELSON
Gas Test 11/22/2022 Corrections Issued MATTHEW NELSON
Sewer 11/22/2022 Corrections Issued MATTHEW NELSON
Wood Frame 11/22/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 11/30/2022 Corrections Issued MATTHEW NELSON
Gas Test 11/30/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Final 11/30/2022 Not Ready for Inspection MATTHEW NELSON
Wood Frame 11/30/2022 No Access for Inspection MATTHEW NELSON
ELECTRICAL-Rough 12/7/2022 Corrections Issued JENNIFER RABUCHIN
Gas Test 12/7/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/7/2022 Approved JENNIFER RABUCHIN
Sewer 12/7/2022 Approved JENNIFER RABUCHIN
Wood Frame 12/7/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 12/14/2022 Approved MATTHEW NELSON
Wood Frame 12/14/2022 Approved MATTHEW NELSON
Insulation 12/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 12/27/2022 Not Ready for Inspection MATTHEW NELSON
Insulation 12/27/2022 Approved MATTHEW NELSON
Drywall Nailing 1/3/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/31/2023 Approved MATTHEW NELSON
Final 1/31/2023 Corrections Issued MATTHEW NELSON
Green Building Final 1/31/2023 Corrections Issued MATTHEW NELSON
Green Building Rough 1/31/2023 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 1/31/2023 Not Ready for Inspection MATTHEW NELSON
Final 2/27/2023 Corrections Issued MATTHEW NELSON
Green Building Final 2/27/2023 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved MATTHEW NELSON
Smoke Detectors 2/27/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 3/13/2023 Approved MATTHEW NELSON
Final 3/13/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 3/13/2023 Approved MATTHEW NELSON
HVAC-Final 3/13/2023 Approved MATTHEW NELSON
PLUMBING-Final 3/13/2023 Approved MATTHEW NELSON