10712 W COLEBROOK ST 91040

Certificate Information: 10712 W COLEBROOK ST 91040

Application / Permit
22016-20000-01302
Plan Check / Job No.
B22VN00652
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE/STORAGE AND ADD A ONE STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/2/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 MOHAMMAD ESMAILI
Corrections Issued 2/20/2022 MOHAMMAD ESMAILI
Quality Review Completed 2/28/2022 OMID HEDAYAT
Building Plans Picked Up 3/1/2022 APPLICANT
Applicant returned to address corrections 12/2/2022 MOHAMMAD ESMAILI
Plan Check Approved 6/1/2023 MOHAMMAD ESMAILI
Issued 6/2/2023 APPLICANT
CofO in Progress 8/30/2025 DAVID ANDERSON
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/14/2022 JOSE DUARTE-DIAZ
Street Frontage Cleared 3/14/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 5/2/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/2/2022 JOSE DUARTE-DIAZ
Distance to fire station Cleared 8/18/2022 LAURINDA MEADE
Hydrant and Access approval Cleared 8/18/2022 LAURINDA MEADE
Specific Plan Cleared 8/30/2022 CECILIA CASTILLO
ZI Cleared 8/30/2022 CECILIA CASTILLO
Construction within easement Cleared 10/26/2022 WALTER RAMIREZ
Grading Pre-Inspection Cleared 4/24/2023 ALEXANDER HELFER
GPI Written Notices Cleared 6/1/2023 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 4/8/2024 Approved DAVID ANDERSON
Sewer 4/8/2024 Approved DAVID ANDERSON
Underground Mechanical 4/8/2024 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 6/7/2024 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 6/7/2024 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 6/13/2024 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 6/13/2024 Approved DAVID ANDERSON
ELECTRICAL-Rough 7/2/2024 Approved DAVID ANDERSON
HVAC-Rough 7/2/2024 Not Ready for Inspection DAVID ANDERSON
Shower Pan 7/2/2024 Approved DAVID ANDERSON
Insulation 8/2/2024 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 9/6/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 9/6/2024 Approved MATTHEW NELSON
HVAC-Rough 9/6/2024 Approved MATTHEW NELSON
Insulation 9/6/2024 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 9/18/2024 Corrections Issued DAVID ANDERSON
HVAC-Rough 9/18/2024 Not Ready for Inspection DAVID ANDERSON
Insulation 9/18/2024 Approved DAVID ANDERSON
Footing/Foundation/Slab 10/31/2024 Corrections Issued DAVID ANDERSON
Deputy Drilled-In Anchors 11/5/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 11/22/2024 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 11/27/2024 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 12/12/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/27/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 4/16/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/21/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/14/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/14/2025 Partial Approval DAVID ANDERSON
Drywall Nailing 5/21/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/21/2025 Approved DAVID ANDERSON
Final 8/8/2025 Corrections Issued DAVID ANDERSON
Green Building Final 8/8/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 8/8/2025 Approved DAVID ANDERSON
Final 8/15/2025 Corrections Issued DAVID ANDERSON
Gas Test 8/15/2025 Approved DAVID ANDERSON
Final 8/20/2025 Not Ready for Inspection DAVID ANDERSON
Final 8/27/2025 OK to Issue CofO DAVID ANDERSON
Green Building Final 8/27/2025 Approved DAVID ANDERSON