10712 W COLEBROOK ST 91040
Certificate Information: 10712 W COLEBROOK ST 91040
- Application / Permit
- 22016-20000-01302
- Plan Check / Job No.
- B22VN00652
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE/STORAGE AND ADD A ONE STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/20/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/28/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| Applicant returned to address corrections | 12/2/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/1/2023 | MOHAMMAD ESMAILI |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 8/30/2025 | DAVID ANDERSON |
| CofO Issued | 9/18/2025 | RUBEN SALAS |
| Permit Finaled | 9/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
| Street Frontage | Cleared | 3/14/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 5/2/2022 | JOSE DUARTE-DIAZ |
| Distance to fire station | Cleared | 8/18/2022 | LAURINDA MEADE |
| Hydrant and Access approval | Cleared | 8/18/2022 | LAURINDA MEADE |
| Specific Plan | Cleared | 8/30/2022 | CECILIA CASTILLO |
| ZI | Cleared | 8/30/2022 | CECILIA CASTILLO |
| Construction within easement | Cleared | 10/26/2022 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 4/24/2023 | ALEXANDER HELFER |
| GPI Written Notices | Cleared | 6/1/2023 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 4/8/2024 | Approved | DAVID ANDERSON |
| Sewer | 4/8/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 4/8/2024 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/7/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 6/7/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/13/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 6/13/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/2/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/2/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 7/2/2024 | Approved | DAVID ANDERSON |
| Insulation | 8/2/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/6/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 9/6/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/6/2024 | Approved | MATTHEW NELSON |
| Insulation | 9/6/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/18/2024 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 9/18/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Insulation | 9/18/2024 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/31/2024 | Corrections Issued | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 11/5/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 11/22/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/27/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/12/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/27/2025 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2025 | Corrections Issued | DAVID ANDERSON |
| Deputy Wood Construction | 4/16/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/14/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 5/21/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/21/2025 | Approved | DAVID ANDERSON |
| Final | 8/8/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 8/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 8/8/2025 | Approved | DAVID ANDERSON |
| Final | 8/15/2025 | Corrections Issued | DAVID ANDERSON |
| Gas Test | 8/15/2025 | Approved | DAVID ANDERSON |
| Final | 8/20/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 8/27/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 8/27/2025 | Approved | DAVID ANDERSON |