804 W BOCCACCIO AVE 90291
Certificate Information: 804 W BOCCACCIO AVE 90291
- Application / Permit
- 22016-20000-01099
- Plan Check / Job No.
- B22VN00557
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL THROUGHOUT (E) SINGLE FAMILY DWELLING. REMOVE WALL BETWEEN KITCHEN AND DINING ROOM. REMODEL KITCHEN AND TWO (E) BATHROOMS. REMOVE AND REPLACE WINDOWS.
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/29/2022
Permit Application Status History
| Submitted | 1/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 1/27/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/14/2022 | JEROME MAGAT PALMA |
| Issued | 2/15/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| Permit Finaled | 11/29/2022 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Coastal Zone | Cleared | 1/31/2022 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 1/31/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | U S Home Developers Inc; Lic. No.: 947505-B | 19737 VENTURA BLVD #310A WOODLAND HILLS, CA 91367 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 6/2/2022 | Not Ready for Inspection | PATRICK QUALEY |
| PLUMBING-Rough | 6/2/2022 | Corrections Issued | PATRICK QUALEY |
| Pre-Inspection | 6/2/2022 | Partial Inspection | PATRICK QUALEY |
| Wood Frame | 6/2/2022 | Partial Approval | PATRICK QUALEY |
| ELECTRICAL-Rough | 6/6/2022 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 6/6/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/6/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 6/16/2022 | Partial Inspection | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Partial Approval | PATRICK QUALEY |
| HVAC-Rough | 6/27/2022 | Approved | PATRICK QUALEY |
| Insulation | 6/29/2022 | Approved | PATRICK QUALEY |
| Deputy Wood Construction | 6/30/2022 | No Access for Inspection | PATRICK QUALEY |
| Drywall Nailing | 7/7/2022 | Approved | DAVID FEILER |
| Gas Test | 7/7/2022 | Partial Approval | DAVID FEILER |
| Shower Pan | 7/7/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 7/13/2022 | Partial Approval | RICHARD STEINBACH |
| Interior/Exterior Lathing | 9/27/2022 | Corrections Issued | DAVID FEILER |
| Gas Test | 10/11/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 10/11/2022 | Partial Approval | CLAYTON GRAHAM |
| ELECTRICAL-Final | 11/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 11/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 11/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/15/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 11/15/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Final | 11/29/2022 | Permit Finaled | JESUS RODRIGUEZ |
| HVAC-Final | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/29/2022 | Approved | JESUS RODRIGUEZ |