1501 W 215TH ST 90501

Certificate Information: 1501 W 215TH ST 90501

Application / Permit
22016-20000-00930
Plan Check / Job No.
B22VN00477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
7 SQFT ADDITION IN KITCHEN W/INTERIOR REMODEL TO THE (E) KITCHEN AND REMOVAL OF A LOAD BEARING WALL.
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
CofO Issued on 1/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2022 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 PETER MOSESIAN
Issued 1/24/2022 APPLICANT
CofO in Progress 11/15/2022 EUGENE CASSIDY
Permit Finaled 1/9/2023 ANSON MAGLASANG
CofO Issued 1/9/2023 ANSON MAGLASANG
Permit Finaled 1/9/2023 ANSON MAGLASANG

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Pro Star Builders Inc; Lic. No.: 1053661-B 17412 VENTURA BLVD SUITE 151      ENCINO, CA 91316
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/9/2022 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 3/9/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 3/9/2022 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 3/9/2022 Approved EUGENE CASSIDY
Drywall Nailing 3/14/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 3/14/2022 Approved EUGENE CASSIDY
Insulation 3/14/2022 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 3/14/2022 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 3/14/2022 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 3/22/2022 Approved EUGENE CASSIDY
Wood Frame 3/22/2022 Approved EUGENE CASSIDY
Drywall Nailing 3/29/2022 Approved EUGENE CASSIDY
Green Building Rough 3/29/2022 Approved EUGENE CASSIDY
Insulation 3/29/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/29/2022 Approved EUGENE CASSIDY
Final 9/29/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 9/29/2022 Approved EUGENE CASSIDY
Green Building Final 9/29/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 9/29/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 10/25/2022 Not Ready for Inspection EUGENE CASSIDY
Final 10/25/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 10/25/2022 Approved EUGENE CASSIDY
HVAC-Final 10/25/2022 Approved EUGENE CASSIDY
HVAC-Rough 10/25/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 10/25/2022 Not Ready for Inspection EUGENE CASSIDY
Final 11/3/2022 Corrections Issued EUGENE CASSIDY
Smoke Detectors 11/3/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 11/14/2022 Approved EUGENE CASSIDY
Final 11/14/2022 OK to Issue CofO EUGENE CASSIDY
PLUMBING-Final 11/14/2022 Approved EUGENE CASSIDY
Smoke Detectors 11/14/2022 Approved EUGENE CASSIDY