2216 S SELBY AVE 90064

Certificate Information: 2216 S SELBY AVE 90064

Application / Permit
22016-20000-00692
Plan Check / Job No.
B22VN00354
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) TWO CAR DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 12/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 SERGIO MUNIZ
Corrections Issued 1/22/2022 SERGIO MUNIZ
Applicant returned to address corrections 2/17/2022 SERGIO MUNIZ
Plan Check Approved 3/4/2022 SERGIO MUNIZ
Building Plans Picked Up 3/8/2022 APPLICANT
Issued 3/18/2022 APPLICANT
CofO in Progress 12/11/2024 DANIEL VERA
CofO Issued 12/28/2024 RICHARD STEINBACH
Permit Finaled 12/28/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 2/1/2022 FREDDY GARCIA
Address approval Cleared 2/3/2022 DINAH GARIN
Sewer availability Cleared 2/3/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/4/2022 DINAH GARIN

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 14263 VALLEY VISTA BLVD.      SHERMAN OAKS, CA 91403
Contractor Kearney Joe Construction; Lic. No.: 612030-B 15127 DEL GADO DRIVE      SHERMAN OAKS, CA 91403

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/29/2022 Approved EVAN COOPER
Footing/Foundation/Slab 4/12/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/21/2022 Conditional Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 5/2/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 5/2/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 5/2/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/2/2022 Partial Approval JOHNNY MIRANDA
METHANE-Rough 5/2/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/2/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 5/3/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Not Ready for Inspection EVAN COOPER
Shower Pan 5/5/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 5/9/2022 Corrections Issued JOHNNY MIRANDA
Interior/Exterior Lathing 5/9/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 3/28/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 3/28/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Approved JESUS PINEDA
HVAC-Rough 3/28/2024 Approved JESUS PINEDA
Insulation 3/28/2024 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 3/28/2024 Approved JESUS PINEDA
Insulation 6/24/2024 Partial Approval SEAN HAUPT
Drywall Nailing 6/25/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 10/31/2024 Corrections Issued KIRK SANDERS
HVAC-Final 10/31/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 10/31/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Final 11/5/2024 Partial Approval KIRK SANDERS
HVAC-Final 11/5/2024 Approved KIRK SANDERS
PLUMBING-Final 11/5/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 11/12/2024 Not Ready for Inspection DANIEL VERA
Final 11/12/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 11/12/2024 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV No Gas DANIEL VERA
Smoke Detectors 11/12/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 11/27/2024 Not Ready for Inspection DANIEL VERA
Final 11/27/2024 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 12/5/2024 Approved DANIEL VERA
Final 12/5/2024 OK to Issue CofO DANIEL VERA
Service/Power Release 12/5/2024 Approved DANIEL VERA