9098 N GULLO AVE 91331
Certificate Information: 9098 N GULLO AVE 91331
- Application / Permit
- 22016-20000-00609
- Plan Check / Job No.
- B22VN00292
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). COMPLY WITH DEPARTMENT ORDER effective date 07/30/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 1/22/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/17/2022 | JEROME MAGAT PALMA |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| CofO in Progress | 10/18/2022 | MICKEY YAMASHITA |
| CofO in Progress | 10/18/2022 | MICKEY YAMASHITA |
| Permit Finaled | 11/2/2022 | DAVID JAMES |
| CofO Issued | 11/2/2022 | DAVID JAMES |
| Permit Finaled | 11/2/2022 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/27/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/11/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 4/11/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 4/20/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 5/5/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 5/10/2022 | Partial Approval | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 5/17/2022 | Approved | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/17/2022 | Partial Approval | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 5/26/2022 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 5/26/2022 | Corrections Issued | MICKEY YAMASHITA |
| HVAC-Rough | 5/26/2022 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/26/2022 | Approved | MICKEY YAMASHITA |
| Sewer | 5/26/2022 | Approved | MICKEY YAMASHITA |
| Underground Mechanical | 5/26/2022 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 6/3/2022 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2022 | Approved | THOMAS WOODS |
| Gas Test | 6/3/2022 | Approved | THOMAS WOODS |
| Green Building Rough | 6/3/2022 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 6/7/2022 | Approved | THOMAS WOODS |
| Insulation | 6/9/2022 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 6/9/2022 | Partial Inspection | THOMAS WOODS |
| PLUMBING-Rough | 6/9/2022 | Approved | THOMAS WOODS |
| Underground Mechanical | 6/9/2022 | Approved | THOMAS WOODS |
| Drywall Nailing | 6/14/2022 | Approved | THOMAS WOODS |
| Final | 9/28/2022 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 9/28/2022 | Approved | MICKEY YAMASHITA |
| PLUMBING-Final | 9/28/2022 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Approved | MICKEY YAMASHITA |
| Smoke Detectors | 9/28/2022 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Final | 10/4/2022 | Approved | MICKEY YAMASHITA |
| Final | 10/4/2022 | Partial Approval | MICKEY YAMASHITA |
| Service/Power Release | 10/4/2022 | Corrections Issued | MICKEY YAMASHITA |
| Smoke Detectors | 10/4/2022 | Approved | MICKEY YAMASHITA |
| Final | 10/18/2022 | OK to Issue CofO | MICKEY YAMASHITA |