9430-9432 N DEMPSEY AVE 91343
Certificate Information: 9430-9432 N DEMPSEY AVE 91343
- Application / Permit
- 22016-20000-00597
- Plan Check / Job No.
- B22VN00287
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE AND 14' X 7'-3" PORTION OF DWELLING TO ACCESSORY DWELLING UNIT (381 SQ FT) PER LAMC 12.22 A.33(c) and (e). COMPLY WITH DEPARTMENT ORDER effective date 10/21/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 1/22/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/10/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 7/26/2022 | MARK DOVICO |
| CofO Issued | 8/26/2022 | DAVID JAMES |
| Permit Finaled | 8/26/2022 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/24/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 2/10/2022 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Golden Construction Group Llc; Lic. No.: 1078364-B | 16814 CITRONIA STREET NORTHRIDGE, CA 91343 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/21/2022 | Approved | MARK DOVICO |
| Insulation | 4/11/2022 | Not Ready for Inspection | MARK DOVICO |
| Interior/Exterior Lathing | 4/11/2022 | Not Ready for Inspection | MARK DOVICO |
| BUILDING-Rough-Frame | 4/13/2022 | Approved | MARK DOVICO |
| ELECTRICAL-Rough | 4/13/2022 | Approved | MARK DOVICO |
| Green Building Rough | 4/13/2022 | Approved | MARK DOVICO |
| Interior/Exterior Lathing | 4/13/2022 | Approved | MARK DOVICO |
| PLUMBING-Rough | 4/13/2022 | Approved | MARK DOVICO |
| Insulation | 4/14/2022 | Approved | MARK DOVICO |
| Drywall Nailing | 4/18/2022 | Approved | ROBERT SUNSERI |
| Wood Frame | 4/20/2022 | Approved | MARK DOVICO |
| Interior/Exterior Lathing | 4/27/2022 | Approved | MARK DOVICO |
| Final | 5/20/2022 | Corrections Issued | MARK DOVICO |
| Green Building Final | 5/20/2022 | Not Ready for Inspection | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 5/20/2022 | SGSOV Approved | MARK DOVICO |
| Smoke Detectors | 5/20/2022 | Approved | MARK DOVICO |
| Pre-Inspection | 5/25/2022 | Approved | MARK DOVICO |
| Final | 6/1/2022 | Conditional Approval | MARK DOVICO |
| Green Building Final | 6/1/2022 | Approved | MARK DOVICO |
| Final | 7/26/2022 | Conditional Approval | MARK DOVICO |