518 N WESTERN AVE 90004
Certificate Information: 518 N WESTERN AVE 90004
- Application / Permit
- 22016-10004-20951
- Plan Check / Job No.
- B24LA06343
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- Supplemental to 22016-30000-20951: Revise Loading space opening and overhand at loading dock
- Permit Issued
- Issued on 4/8/2024
- Issuing Office
- Current Status
- Permit Finaled on 7/16/2025
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | HERNAN ARREOLA |
| Plan Check Approved | 4/8/2024 | HERNAN ARREOLA |
| Issued | 4/8/2024 | APPLICANT |
| Permit Finaled | 7/16/2025 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Red Stag Construction Company; Lic. No.: 964664-B | 9948 SEPULVEDA BLVD #6 MISSION HILLS, CA 91345 |
| Engineer | Melnyk,, Matthew; Lic. No.: S5853 | 600 WILSHIRE BLVD, SUITE 760 SUITE 760 LOS ANGELES, CA 90017 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/17/2024 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 4/17/2024 | Partial Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 4/22/2024 | Approved | TIMOTHY POWELL |
| Footing/Foundation/Slab | 4/22/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 5/6/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 5/6/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/24/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 5/31/2024 | Partial Inspection | TIMOTHY POWELL |
| Masonry Wall/Backfill | 6/20/2024 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 7/15/2024 | Partial Approval | RAFAEL CORTES |
| Masonry Wall/Backfill | 7/24/2024 | Partial Approval | LUIS CCAMACHO |
| Deputy Drilled-In Anchors | 8/15/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 8/19/2024 | Partial Approval | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 1/29/2025 | Partial Inspection | TIMOTHY POWELL |
| Structural Steel Frame | 1/29/2025 | Partial Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 3/19/2025 | Partial Approval | TIMOTHY POWELL |
| Structural Steel Frame | 3/19/2025 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 3/27/2025 | Approved | TIMOTHY POWELL |
| Final | 7/16/2025 | Permit Finaled | RAFAEL ESPINOZA |
| Smoke Detectors | 7/16/2025 | Approved | RAFAEL ESPINOZA |