202 1/2 E 108TH ST 90061

Certificate Information: 202 1/2 E 108TH ST 90061

Application / Permit
22016-10003-06081
Plan Check / Job No.
B23LA07242
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO 22016-10002-06081 for the expansion of New Floor Area to ADU
Permit Issued
Issued on 10/31/2023
Issuing Office
Current Status
Permit Finaled on 10/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2023 APPLICANT
Assigned to Plan Check Engineer 4/24/2023 ZAW HAN
Corrections Issued 4/27/2023 ZAW HAN
Building Plans Picked Up 5/1/2023 APPLICANT
Plan Check Approved 10/12/2023 ZAW HAN
Issued 10/31/2023 APPLICANT
Permit Finaled 9/29/2025 ANTHONY EGSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/18/2023 JEANIE LAM
Sewer availability Cleared 9/18/2023 JEANIE LAM
Low Impact Development (LID) Cleared 10/3/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/12/2023 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/1/2023 Approved JAMES CHAVEZ
Underground Mechanical 12/1/2023 Partial Approval JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 1/8/2024 Corrections Issued JOHN KLARIN
Gas Test 1/8/2024 Approved JOHN KLARIN
PLUMBING-Rough 1/8/2024 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 5/3/2024 Approved BEN MOLSTAD
Gas Test 5/3/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 5/3/2024 Corrections Issued BEN MOLSTAD
Gas Test 7/1/2024 No Access for Inspection JAMES CHAVEZ
PLUMBING-Rough 7/1/2024 No Access for Inspection JAMES CHAVEZ
Gas Test 7/5/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 7/5/2024 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/12/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 2/14/2025 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/14/2025 Partial Approval JOSEPH MCGARRY
Green Building Rough 2/14/2025 Approved JOSEPH MCGARRY
HVAC-Rough 2/14/2025 Partial Inspection JOSEPH MCGARRY
PLUMBING-Rough 2/14/2025 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/25/2025 Approved ANSON MAGLASANG
HVAC-Rough 2/25/2025 Approved ANSON MAGLASANG
Interior/Exterior Lathing 2/25/2025 Not Ready for Inspection ANSON MAGLASANG
Insulation 3/12/2025 Approved ANTHONY EGSON
Drywall Nailing 3/17/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/17/2025 Approved ANTHONY EGSON
Shower Pan 3/17/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/28/2025 Approved EUGENE CASSIDY
Final 8/15/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 8/15/2025 Approved ANTHONY EGSON
Green Building Final 8/15/2025 Corrections Issued ANTHONY EGSON
Smoke Detectors 8/15/2025 Approved ANTHONY EGSON
Final 9/29/2025 Permit Finaled ANTHONY EGSON
Green Building Final 9/29/2025 Approved ANTHONY EGSON