12310 W VENICE BLVD 90066
Certificate Information: 12310 W VENICE BLVD 90066
- Application / Permit
- 22016-10001-36170
- Plan Check / Job No.
- B24LA23679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- *emailed Arsalan/Chad on 09/17* Attn: Arsalan Shabestari Supplemental Building Plan Check Revision of Patio Fence: Relocation of the gate to the center of the fence. Adjustment of Path of Travel from Parking Area to building back entrance.
- Permit Issued
- Issued on 10/31/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/3/2026
Permit Application Status History
| Submitted | 9/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 9/26/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/21/2024 | ARSALAN SHABESTARI |
| Issued | 10/31/2024 | APPLICANT |
| Permit Finaled | 4/3/2026 | FARHAD DADBIN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Capasso Construction Inc; Lic. No.: 333398-B | , |
| Engineer | Howe,, Carl William; Lic. No.: NA44773 | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/5/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Insulation | 12/6/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 12/13/2024 | Approved | FARHAD DADBIN |
| Final | 4/3/2026 | Permit Finaled | FARHAD DADBIN |