1045 N ARDMORE AVE 90029

Certificate Information: 1045 N ARDMORE AVE 90029

Application / Permit
22016-10001-08231
Plan Check / Job No.
B22LA26029
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SUPPLEMENTAL TO PERMIT 22016-10000-08231 TO REVISE THE WORK DESCRIPTION TO "ADDITION AND CONVERT (E) PARKING SPACE TO ATTACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C)"
Permit Issued
Issued on 12/27/2022
Issuing Office
Valley
Current Status
Permit Finaled on 1/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 12/22/2022 DANIEL YIP
Issued 12/27/2022 APPLICANT
Permit Finaled 1/18/2024 RONALD JIMENEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Fgc Construction Inc; Lic. No.: 920242-B 5826 OSBUN RD      SAN BERNARDINO, CA 92404
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

RONALD JIMENEZ, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI
JOHN YAKUBYAN, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN QUACH, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2023 Partial Inspection VAHE KELEDJIAN
Deputy Drilled-In Anchors 5/9/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/23/2023 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 5/23/2023 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 6/23/2023 Partial Inspection RONALD JIMENEZ
Wood Frame 7/26/2023 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 8/8/2023 Conditional Approval MARTIN TAVITIAN
Interior/Exterior Lathing 8/15/2023 Partial Approval RAFAEL CORTES
Wood Frame 8/15/2023 Not Ready for Inspection RAFAEL CORTES
Wood Frame 8/21/2023 Not Ready for Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Not Ready for Inspection TIMOTHY POWELL
Wall Anchors 8/29/2023 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 8/29/2023 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 9/1/2023 Not Ready for Inspection TIMOTHY POWELL
Insulation 9/5/2023 Not Ready for Inspection GREGORY POMISH
Insulation 9/12/2023 Approved RONALD JIMENEZ
Wood Frame 9/12/2023 Approved RONALD JIMENEZ
Drywall Nailing 9/15/2023 Not Ready for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 9/15/2023 Partial Approval RONALD JIMENEZ
Special/Order Compliance 9/18/2023 Partial Inspection TIMOTHY POWELL
Drywall Nailing 9/20/2023 Approved RONALD JIMENEZ
Interior/Exterior Lathing 9/20/2023 Partial Approval RONALD JIMENEZ
Final 1/10/2024 Not Ready for Inspection JACOB MYERS
Final 1/18/2024 Permit Finaled RONALD JIMENEZ