3710 S RAYMOND AVE 90007
Certificate Information: 3710 S RAYMOND AVE 90007
- Application / Permit
- 22016-10001-05777
- Plan Check / Job No.
- B22LA15482
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 22016-20000-05777: EXPAND EXTENT OF DEMOLITION AND STRUCT. CHANGES TO SLAB AND ROOF FRAMING. REPLACE NON-CONFIRMING WINDOWS SAME DIMENSION AND LOCATION
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/11/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 8/16/2022 | KHUONG TRUONG |
| Issued | 8/16/2022 | APPLICANT |
| Building Plans Picked Up | 8/16/2022 | APPLICANT |
| Permit Finaled | 4/2/2024 | JOHN PARKER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2022 | Approved | ENRIQUE PREZA |
| Pre-Inspection | 12/6/2022 | Approved | ENRIQUE PREZA |
| Deputy Drilled-In Anchors | 5/4/2023 | No Access for Inspection | DANIEL GONZALEZ |
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Not Ready for Inspection | ENRIQUE PREZA |
| Pre-Inspection | 5/8/2023 | Not Ready for Inspection | ENRIQUE PREZA |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Partial Approval | ENRIQUE PREZA |
| Footing/Foundation/Slab | 5/24/2023 | Approved | ENRIQUE PREZA |
| Pre-Inspection | 5/24/2023 | Corrections Issued | ENRIQUE PREZA |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Partial Approval | ENRIQUE PREZA |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | ENRIQUE PREZA |
| Wood Frame | 7/18/2023 | Partial Approval | ENRIQUE PREZA |
| Wood Frame | 8/4/2023 | Not Ready for Inspection | ENRIQUE PREZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Approved | ENRIQUE PREZA |
| Deputy Drilled-In Anchors | 8/23/2023 | Partial Approval | ENRIQUE PREZA |
| Insulation | 8/24/2023 | Approved | ENRIQUE PREZA |
| Interior/Exterior Lathing | 8/24/2023 | Approved | ENRIQUE PREZA |
| Wood Frame | 8/24/2023 | Approved | ENRIQUE PREZA |
| Drywall Nailing | 9/5/2023 | Approved | DANIEL GONZALEZ |
| Final | 3/26/2024 | No Access for Inspection | JAVIER RAMOS SR |
| Smoke Detectors | 3/26/2024 | No Access for Inspection | JAVIER RAMOS SR |
| Final | 4/2/2024 | Permit Finaled | JOHN PARKER |
| Smoke Detectors | 4/2/2024 | Approved | JOHN PARKER |