1938 S HARVARD BLVD 90018
Certificate Information: 1938 S HARVARD BLVD 90018
- Application / Permit
- 22016-10001-03890
- Plan Check / Job No.
- B22LA23608
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN Supplemental to permit # 22016-10000-03864.for building 2 FOR ADDITIONAL SCOPE OF WORK TO SINGLE PODIUM BUILDING. Revisions for this permit include; reconfiguring units in building 2 to provide an additional 3-bedroom mobility unit and 4-bedroom mobility unit to comply with dispersion requirements, including two small bathroom additions. Providing accessible parking spaces and two wheel chair lifts to connect the newly designated lower level accessible route to the newly designated accessible pedestrian and ground level circulation route.
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Current Status
- CofO Issued on 9/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 1/18/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/23/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/16/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/24/2023 | ARSALAN SHABESTARI |
| Issued | 4/20/2023 | APPLICANT |
| CofO in Progress | 8/23/2024 | LUIS CCAMACHO |
| CofO in Progress | 9/9/2024 | JEROME BLACKWOOD |
| CofO in Progress | 9/10/2024 | JEROME BLACKWOOD |
| CofO Issued | 9/10/2024 | ERNESTO CORRAL |
| Permit Finaled | 9/10/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 1/31/2023 | LOUIS ORTEGA |
| Roof/Waste drainage to street | Cleared | 2/5/2023 | ADRIAN SANCHEZ |
| HPOZ | Cleared | 2/6/2023 | MICAELA TORRES-GIL |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/7/2023 | ADRIAN SANCHEZ |
| Green Code | Cleared | 2/22/2023 | Kevin Morales |
| Hydrant and Access approval | Cleared | 2/22/2023 | JOHN CONNEALLY |
| DAS Clearance | Cleared | 3/2/2023 | Kevin Morales |
| Public Housing | Cleared | 3/17/2023 | RONALD PACHECO |
Contact Information
| Contractor | Precision General Commercial Contractors Inc; Lic. No.: 790153-B | 7250 REDWOOD BLVD STE 214 NOVATO, CA 94945 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Partial Approval | RONALD JIMENEZ |
| Final | 12/18/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Footing/Foundation/Slab | 12/18/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Final | 12/18/2023 | Not Ready for Inspection | RICARDO ROBLES |
| Green Building Rough | 12/18/2023 | Not Ready for Inspection | RICARDO ROBLES |
| METHANE-Barrier | 12/18/2023 | No Access for Inspection | MARTIN TAVITIAN |
| METHANE-Final | 12/18/2023 | Not Ready for Inspection | RICARDO ROBLES |
| METHANE-Rough | 12/18/2023 | Not Ready for Inspection | RICARDO ROBLES |
| METHANE-Subgrade | 12/18/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Smoke Detectors | 12/18/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Wood Frame | 12/18/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Final | 12/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 12/20/2023 | Approved | JEROME BLACKWOOD |
| Green Building Final | 12/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 12/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Barrier | 12/20/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Final | 12/20/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 12/20/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Subgrade | 12/20/2023 | Approved | JEROME BLACKWOOD |
| Smoke Detectors | 12/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 12/20/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 8/12/2024 | OK to Issue CofO | JEROME BLACKWOOD |
| Green Building Final | 8/12/2024 | Approved | JEROME BLACKWOOD |
| Green Building Rough | 8/12/2024 | Approved | JEROME BLACKWOOD |
| Smoke Detectors | 8/12/2024 | Approved | JEROME BLACKWOOD |
| Wood Frame | 8/12/2024 | Approved | JEROME BLACKWOOD |
| Final | 8/20/2024 | OK to Issue CofO | JEROME BLACKWOOD |
| Wood Frame | 8/20/2024 | Approved | JEROME BLACKWOOD |
| Final | 8/23/2024 | OK to Issue CofO | LUIS CCAMACHO |
| Wood Frame | 8/23/2024 | Approved | LUIS CCAMACHO |