832 S HILGARD AVE 90024

Certificate Information: 832 S HILGARD AVE 90024

Application / Permit
22016-10001-02189
Plan Check / Job No.
B24LA00898
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(11) Dormitory
Work Description
SUPPLEMENTAL TO 22016-30000-02189 TO REVISE FLOOR PLAN (NO IMPROVEMENT ON 3RD FLOOR).
Permit Issued
Issued on 3/21/2024
Issuing Office
Metro
Current Status
Permit Finaled on 7/15/2024

Permit Application Status History

Submitted 1/18/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 AUNG SOE
Corrections Issued 1/29/2024 AUNG SOE
Quality Review Completed 1/29/2024 EUGENE BARBEAU
Building Plans Picked Up 1/30/2024 APPLICANT
Disabled Access Plans Picked Up 2/6/2024 APPLICANT
Plan Check Approved 3/21/2024 AUNG SOE
Issued 3/21/2024 APPLICANT
Permit Finaled 7/12/2024 PAUL DAVIDSON

Permit Application Clearance Information

DAS Clearance Cleared 1/27/2024 SHINE LIN
Fire Marshal Fire Life Safety Cleared 3/15/2024 ANDREW KO

Contact Information

Architect Mark, A Besquin; Lic. No.: C39073 10877 ROSE AVE   5    LOS ANGELES, CA 90034
Contractor Bloomfield Construction Inc; Lic. No.: 1091558-B 8113 COOPER LN      GARDENA, CA 90248

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 3/26/2024 Partial Approval RICARDO ROBLES
Wood Frame 3/26/2024 Partial Approval RICARDO ROBLES
Final 7/12/2024 Permit Finaled PAUL DAVIDSON